Student Health and Counseling Center
Create an identifiable and easily accessible facility that welcomes members of our diverse campus community and conveys a commitment to quality care, innovation in technical, medical and clinical services, student support and well being. This facility aligns with the missions and values of the UCR campus, the Division of Student Affairs, Student Health Services, Counseling and Psychological Services, Student Affairs Case Management, and The Well that support student retention and success through optimization of emotional and physical health, through direct service, promotion, prevention, education, student engagement, and provision of resources and referrals.
Project Scope:
- The new SHCC will further improve health, counseling and wellness services currently provided at the Campus
- It will offer integrated and holistic care in a welcoming and student-centered environment, with increased medical and mental health providers on staff
- The design of the SHCC should address the students’ experience
- In addition to providing medical and mental health services, the new facility is envisioned as a destination within the UCR Campus
- While the current Student Health Center is relatively insular, the new SHCC should be more visible and become an integral part of the UCR Campus
- Different programs within the SHCC will share common resources and they will be administered accordingly
- The SHCC building space should provide opportunities for collaboration, be flexible and have room for growth
- To best serve the significant number of commuter students. t the SHCC should be a comfortable and welcoming space that accommodates these students while waiting for appointments
Student Health & Counseling Center Construction Updates
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #18
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continue shotcrete installation
Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.
Project Site
Continue underground utility installation
Mini Excavator, various hand tools
Moderate level of vehicle engine and pedestrian noise.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Week of 6-27-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continue shotcrete installation
Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.
Project Site
Remove concrete wall forms
Mini Excavator, various hand tools
Moderate level of vehicle engine, backup warning sounds and pedestrian noise.
Project Site
Continue underground utility installation
Mini Excavator, various hand tools
Moderate level of vehicle engine, backup warning sounds and pedestrian noise.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Upcoming Anticipated Utility Shutdowns
The following utility shutdown(s) are anticipated in the weeks to come. Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.
Description
Location
Proposed
Duration & Date
Potential Impacted Buildings/ Facilities
None anticipated at this time
-
-
-
Biweekly Neighborhood Meetings are scheduled every other Mondays at 2:00 pm where construction impacts to the adjacent areas are discussed and how those issues can be addressed or mitigated. If you would like to be added to the list of attendees, or if you would like us to include additional attendees, please respond to this email with the required contact information.
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #17
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Concrete wall form installation
Rough Terrain Forklift, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Project Site
Concrete Wall Pour
Concrete Pump, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Project Site
Underground utility installation
Mini Excavator, various hand tools
Moderate level of vehicle engine and pedestrian noise.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Week of 6-27-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continue concrete wall form installation
Rough Terrain Forklift, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Project Site
Continue shotcrete installation
Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.
Project Site
Continue underground utility installation
Mini Excavator, various hand tools
Moderate level of vehicle engine and pedestrian noise.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Upcoming Anticipated Utility Shutdowns
The following utility shutdown(s) are anticipated in the weeks to come. Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.
Description
Location
Proposed
Duration & Date
Potential Impacted Buildings/ Facilities
None anticipated at this time
-
-
-
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #16
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Concrete wall form installation
Rough Terrain Forklift, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Project Site
Shotcrete installation
Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Week of 6-13-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Concrete wall form installation
Rough Terrain Forklift, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Project Site
Shotcrete installation
Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.
Dundee-Glasgow Access Road at Linden
Utility Shutdown: Domestic water connection
Contractor Work Trucks
On June 17 from 7am to 5pm, one lane of Dundee- Glasgow access road will be closed. During this time, access to and from Linden to Glasgow Dining Hall will be controlled by flag people.
Pentland Hills Residence Halls,
Building I, J, K and L
Utility Shutdown: Domestic water connection
Contractor Work Trucks
Pentland Hills Residence Halls,
Building I, J, K and L will be without water for 10 hours on June 17 from 7am to 5pm.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Upcoming Anticipated Utility Shutdowns
The following utility shutdown(s) are anticipated in the weeks to come. Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.
Description
Location
Proposed
Duration & Date
Potential Impacted Buildings/ Facilities
Sewer connection
Landscape area between Dundee and Glasgow
Date: N/A
This work will not result in a utility shutdown as originally anticipated. Sewer service will remain operational during construction.
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #15
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #15
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continued foundation concrete forms and rebar installation
Rough Terrain Forklift, Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Project Site
Continued foundation concrete pouring
Concrete Pumper Truck, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Week of 6-6-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continued foundation concrete forms and rebar installation
Rough Terrain Forklift, Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Project Site
Continued foundation concrete pouring
Concrete Pumper Truck, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Upcoming Anticipated Utility Shutdowns
The following utility shutdown(s) are anticipated in the weeks to come. Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.
Description
Location
Proposed
Duration & Date
Potential Impacted Buildings/ Facilities
Domestic water connection
Pentland Hills Residence Halls,
Building I, J, K and L
Duration: 8 hours
Dates: Friday, June 17
Pentland Hills Residence Halls,
Building I, J, K and L will likely be without water for 8 hours;
Domestic water connection
Dundee access road at Linden
Dates:
Monday, June 13 to
Friday, June 17
Periodically, one lane of Dundee- Glasgow access road will be closed. During that time, access to and from Linden to Glasgow Dining Hall will be controlled by flag people.
Sewer connection
Landscape area between Dundee and Glasgow
Duration: TBD
Date: TDB
Details of this utility shutdown are in progress. Please reach out to Dexter Galang at dexter.galang@ucr.edu with any concerns or questions.
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #14
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continued foundation concrete forms and rebar installation
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Project Site
Continued foundation concrete pouring
Concrete pumper truck, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Week of 5-30-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continued foundation concrete forms and rebar installation
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Project Site
Continued foundation concrete pouring
Concrete pumper truck, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Upcoming Anticipated Utility Shutdowns
The following utility shutdown(s) are anticipated in the weeks to come. Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.
Description
Location
Proposed
Duration & Date
Potential Impacted Buildings/ Facilities
Domestic water connection
Dundee access road at Linden and Pentland Hills Residence Halls,
Building I, J, K and L
Duration: 8 hours
Date: Friday, June 17
Pentland Hills Residence Halls,
Building I, J, K and L will likely be without water for 8 hours;
One lane of Dundee- Glasgow access road will be closed. Traffic will be controlled by flag people.
Sewer connection
Landscape area between Dundee and Glasgow
Duration: TBD
Date: TDB
Details of this utility shutdown are in progress. It will also be discussed at the next Biweekly Neighborhood Meeting next Monday, May 30. Please reach out to Dexter Galang at dexter.galang@ucr.edu with any concerns, questions or if you would like to attend that meeting.
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #13
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continued foundation excavation and rebar installation
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Week of 5-23-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continued foundation excavation and rebar installation
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Project Site
Foundation Concrete Pouring
Concrete pumper truck, Concrete Mixer Truck, various hand tools
Increased truck traffic along Linden from concrete truck deliveries.
Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.
Dundee-Glasgow Access Road
Utility Investigation/ potholing
Vacuum excavator
One lane of Dundee- Glasgow access road will be closed. Traffic will be controlled by flag people.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Live Earthcam link available soon!
Upcoming Anticipated Utility Shutdowns
The following utility shutdown is anticipated in the weeks to come. Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.
Description
Location
Proposed
Duration & Date
Potential Impacted Buildings/ Facilities
Domestic water connection
Dundee access road at Linden and Pentland Hills Residence Halls,
Building I, J, K and L
Duration: 8 hours
Date: Friday, June 17
Pentland Hills Residence Halls,
Building I, J, K and L will likely be without water for 8 hours;
Temporary water option is currently being explored.
One lane of Dundee- Glasgow access road will be closed. Traffic will be controlled by flag people.
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #12
Please be advised that the following activities will be occurring during the weeks/ dates noted below at the Student Health & Counseling Center (SHCC) project site and surrounding areas during construction work hours (7am to 5pm). The activities will occur within the areas identified and the contractor will access the Project Site as shown in the map below.
The Student Health & Counseling Center Building Team recognizes that construction activities will pose inconveniences and disruption to the surrounding neighborhood. We thank you for your continued patience during the construction of this much needed project.
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continued foundation excavation and rebar installation
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Week of 5-16-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continued foundation excavation and rebar installation
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Occasional increased slow traffic due to truck deliveries.
Sidewalk will be open but alternate paths are encouraged.
Dundee Access Road
Utility Investigation/ potholing
Vacuum excavator
Limited access of Dundee Access Road
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Live Earthcam link available soon!
Upcoming Anticipated Utility Shutdowns
The following utility shutdown is anticipated in the weeks to come. Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.
Location
Proposed
Duration & Date
Description
Potential Impacted Buildings/ Facilities
Dundee access road at Linden
Duration: 8 hours
Date: TBD, will occur on a day between June 12 through June 18
Domestic water connection
Pentland Hills Residence Halls,
Building I, J, K and L will likely be without water for 8 hours;
Limited access through the Dundee Access Road
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #11
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Earthwork & Grading
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Sidewalk will be open but alternate paths are encouraged.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Week of 5-2-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Foundation Excavation
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Sidewalk will be open but alternate paths are encouraged.
Linden Street at TAPS Parking Lot
Temporary Power Installation
Contractor Vehicles, various hand tools
Low level of vehicle and pedestrian noise. Brief traffic disturbances.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Live Earthcam link available soon!
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #10
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Earthwork & Grading
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Sidewalk will be open but alternate paths are encouraged.
Linden Street, Pentland Way, and South drive lane of remaining Parking Lot 21
(see plan below)
Earthwork, Grading & Soil Import
Semi-trucks and Trailers
Increased traffic during soil import operations anticipated on Friday, 4-15 from 8am to 4pm.
Street closures not anticipated.
Staging outside of the jobsite also not anticipated at this point.
See diagram below for truck route in and out of the project site.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
Week of 4-18-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Earthwork & Grading
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Sidewalk will be open but alternate paths are encouraged.
Linden Street, Pentland Way, and South drive lane of remaining Parking Lot 21
(see plan below)
Earthwork, Grading & Soil Import
Semi-trucks and Trailers
Continued increased traffic during soil import operations anticipated beginning Monday, 4-18 to Friday 4-22 from the hours of 8am to 4pm.
Street closures not anticipated.
Staging outside of the jobsite also not anticipated.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #9
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continue underground utility relocation work within planting area along sidewalk of Linden
Excavator, backhoe, trencher, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors. Sidewalk will be open but alternate paths are encouraged.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
TAPS and EH&S Building
Weekend Power Switchovers
Trailered Generator, various hand tools
1 hour power outage beginning Saturday, April 8 at approximately 7:00-8:00am and Sunday, April 9 at approximately 3:00-4:00pm
TAPS Building
Data/ Communications Cable Installation
Various hand tools, contractor vehicles
Data/ Communications shutdown beginning Saturday, April 8 at approximately 8:00 am to Sunday, April 9 at approximately 4:00pm.
Fire watch will be in place for the duration of the data/com shutdown.
Dundee Access Road
Data/ Communications Cable Installation
Cable Spools, various hand tools, contractor vehicles
Full road closure beginning approximately Saturday, April 8 at 8 am to 5 pm and Sunday, April 9, 8am to 4pm.
Access will be available for deliveries to and from Glasgow Dining Hall during that time.
The road will be open to traffic after construction work hours.
TAPS/ EH&S Backlot
Weekend operation of backup power generator and removal of backup power generator
Truck and Trailered Generator, various hand tools
Moderate level of sustained running motor beginning approximately April 8 at 8am to April 9 at 1pm. Disconnection of generator and haul away will occur on April 9 at approximately 2:00pm.
Week of 4-11-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Earthwork & Grading
Excavator, semi-trucks, backhoe, loader, grader, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.
Sidewalk will be open but alternate paths are encouraged.
Linden Street, Pentland Way, and South drive lane of remaining Parking Lot 21
(see plan below)
Earthwork, Grading & Soil Import
Semi-trucks and Trailers
Increased traffic during soil import operations anticipated on Friday, 4-15 from 8am to 4pm.
Street closures not anticipated.
Staging outside of the jobsite also not anticipated at this point.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
-
950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #8
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continue underground utility relocation work within planting area along sidewalk of Linden
Excavator, backhoe, trencher, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors. Sidewalk will be open but alternate paths are encouraged.
Contractor Parking Area
Continued parking for contractor and sub-contractors; storage of equipment
Contractor vehicles
Low level of vehicle and pedestrian noise.
Contractor Offices
Office Use
Office Equipment and Furniture
Low level of pedestrian noise
TAPS/ EH&S Backlot
Installation and weekend operation of backup power generator
Truck and Trailered Generator, various hand tools
Friday, April 1 afternoon installation beginning approximately 3pm.
Moderate level of sustained running motor beginning April 2 at approximately 8am to April 3 at approximately 1pm.
TAPS and EH&S Building
Weekend Power Switchovers
Trailered Generator, various hand tools
1 hour power outage beginning Saturday, April 2 at approximately 8:00-9:00am and Sunday, April 3 at approximately 12:00-1:00pm
Dundee Access Road at Linden
Weekend Dundee Access Road Vault investigation
Jack hammer, Backhoe/excavator with breaker, Contractor work vehicles.
Partial road closure beginning Saturday, April 2 at approximately 8 am to 5 pm Sunday, April 3, approximately 8am to 1pm. There will be a high level of sustained construction noise primarily comprised of chipping and banging
Week of 4-4-2022
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Project Site
Continue underground utility relocation work within planting area along sidewalk of Linden
Excavator, backhoe, trencher, & various hand tools
Moderate level of sustained construction noise primarily comprised of running motors. Sidewalk will be open but alternate paths are encouraged.