School of Medicine Building II
The University of California Riverside proposes to construct the School of Medicine (SOM) Education Building II, a new facility of approximately 57,000 assignable square feet (ASF) that will directly support the academic and programmatic mission of the UCR School of Medicine by providing adequate space for existing needs, as well as allowing for future expansion of the class size (up to 125 students per class).
The proposed building is anticipated to provide up to 57,000 assignable square feet (ASF) within approximately 90,000 gross square feet (GSF). The space program will incorporate the following types of spaces, to complement SOM's existing program:
Project Scope:
- Build instruction and instructional support spaces such as classrooms, specialized teaching spaces, and lecture halls;
- Create student support and study facilities including study/lounge spaces necessary to comply with accreditation standards;
- Include academic and administrative offices and support spaces
School of Medicine Education Building II Updates
-
954045 SOM ED II - Construction Alert #92
03/18/2023-03/25/2023
954045 SOM ED II Construction Alert #92
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, March 18th & Sunday, March 19th.
Saturday, March 18th
Building Site:
- Millennium Fire Protection – L4 & L5 Drops @ Hard Lids
- SoCal Coatings: Paint L4 & L5
- Pacific Coast Glazing – Level 1 North – Glazing at Clearstory Windows above I-Beam
- MCI – Continue Grand Stair & Level 1 NorthWest Brick Install
- AO Reed – Sheet Metal: Level 1 Hard Lid Linears
- SDI (Drywall) – Hard Lids at L2 & L5
- SDI (Tapers) – Level 1 Taping
- Biggie – Material Hoist Dismantle
- Buxcon – Level 1 Sill Flashing
- Hensel Phelps – Assist Material Hoist Dismantle
- Please be advised on Saturday 03/18 we will be closing down the temporary loading dock activities from 7 AM – 4 PM due to Material Hoist Demo.
- Anticipated disturbances: Medium-level construction noise on Building Site.
Sunday, March 19th
Building Site:
- MCI – Continue Grand Stair & Level 1 NorthWest Brick Install
- Pacific Coast Glazing – Continue Level 1 North Glazing
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of March 20th through March 25th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue Underground Hydronic Piping activities at South Fire Road. (Equipment: Excavator, various hand and power tools).
- Demo Material Hoist Lift. (Equipment: Various hand and power tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Continue Exterior ACM Metal Panel Installation & Flashings (Equipment: Various hand and power tools).
- Continue Curtain Wall Framing & Glazing at all levels. (Equipment: Various hand and power tools).
- Pour Level 1 Loading Dock. (Equipment: Various hand and power tools).
- Please be advised on Monday 03/20 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
- Anticipated disturbances: Medium-level construction noise on Building Site.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Pour Oak Grove Ramp. (Equipment: Various hand and power tools).
- Please be advised on Thursday 03/23 we will be placing concrete. Anticipated timeline 6 AM – 9 AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
· Anticipated disturbances: Low-level construction noise contained in the surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
-
954045 SOM ED II - Construction Alert #91
03/11/2023-03/18/2023
954045 SOM ED II Construction Alert #91
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, March 11th.
Building Site:
- SoCal Coatings: Paint L3 Ceiling / L5 Hardlid @ Stair 6
- Pacific Coast Glazing – Above Oculus + Stair 6
- MCI – Grand Stair Brick Install
- AO Reed – Sheet Metal: Level 2 Ductwork
- CSI – L3 Lighting
- AO Reed – Piping: HRC + Pump Room
- AO Reed – UG. Piping: Hydronic
- PPM – Roof Water Heater
- Please be advised on Saturday 03/11 we will be shutting down East Campus Drive for the crane pick of the Heat Recovery Chiller. Anticipated timeline 6:00 AM – 2:00 PM.
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of March 13th through March 18th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue Underground Hydronic Piping activities at South Fire Road. (Equipment: Excavator, various hand and power tools).
- Demo Material Hoist Lift. (Equipment: Various hand and power tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Continue Exterior ACM Metal Panel Installation & Flashings (Equipment: Various hand and power tools).
- Continue Curtain Wall Framing & Glazing at all levels. (Equipment: Various hand and power tools).
- Pour Level 1 Loading Dock. (Equipment: Various hand and power tools).
- Please be advised on Friday 03/17 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
- Anticipated disturbances: Medium-level construction noise on Building Site.
- Upcoming Work 03/18/2023: Please be advised on Saturday 03/18 we will be closing down the temporary loading dock activities from 7:00 AM – 4:00 PM due to Material Hoist Demo.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Pour Oak Grove Ramp. (Equipment: Various hand and power tools).
- Please be advised on Thursday 03/16 we will be placing concrete. Anticipated timeline 6 AM – 9 AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
· Anticipated disturbances: Low-level construction noise contained in the surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
- Upcoming Work 03/18/2023: Please be advised on Saturday 03/18 we will be closing down the temporary loading dock activities from 7:00 AM – 4:00 PM due to Material Hoist Demo.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
-
954045 SOM ED II - Construction Alert #90
Correction below to 03/09
03/04/2023-03/11/2023
954045 SOM ED II Construction Alert #90
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, March 04th.
Building Site:
- SDI – Level 5, Oculus & Shaft Taping. Framing/Drywall go backs.
- Pacific Coast Glazing – Level 4 & 5 North East & Stair 6 CW Framing
- AO Reed – Sheet Metal: Level 1 Ductwork
- AO Reed – Piping: Underground Exterior work at South road
- HP – FRP 10” Curb @ GL 3-4
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of March 06th through March 11th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue Underground Hydronic Piping activities at South Fire Road. (Equipment: Excavator, various hand and power tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Continue Exterior ACM Metal Panel Installation & Flashings (Equipment: Various hand and power tools).
- Continue Curtain Wall Framing & Glazing at all levels. (Equipment: Various hand and power tools).
- Pour landing at Stair 3. (Equipment: Various hand and power tools).
- Please be advised on Monday 03/06 we will be placing concrete. The concrete truck will be coming in through the West Courtyard which will cause Interruptions at the loading dock ramp between 8 am – 12 pm. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Anticipated disturbances: Medium-level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Pour Oak Grove Ramp Footings. (Equipment: Various hand and power tools).
- Please be advised on Thursday 03/
0609 we will be placing concrete. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
- Please be advised on Thursday 03/
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
-
954045 SOM ED II - Construction Alert #89
02/25/2023-03/05/2023
954045 SOM ED II Construction Alert #89
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, February 25th.
Building Site:
- ProSteel – Oculus HSS member work
- SDI – Taping Level 5
- Pacific Coast Glazing – Level 5 North Glazing Sealant
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of February 27th through March 04th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Continue Exterior ACM Metal Panel Installation & Flashings (Equipment: Various hand and power tools).
· Continue Curtain Wall Framing & Glazing at all levels. (Equipment: Various hand and power tools).
· Install RediStairs at Stair 3. (Equipment: Various hand and power tools).
· Please be advised on Thursday 03/02 we will be utilizing a crane to unload/load the RediStairs from the West Courtyard. Anticipated timeline 9AM – 12PM (Two – 30 min. interruptions at Loading Dock ramp).
Anticipated disturbances: Medium-level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Pour Oak Grove Ramp Footings. (Equipment: Various hand and power tools).
- Please be advised on Thursday 03/02 we will be placing concrete. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised on Thursday 03/02 we will be placing concrete. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open at all other times and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
-
954045 SOM ED II - Construction Alert #88
02/18/2023-02/25/2023
954045 SOM ED II Construction Alert #88
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, February 18th.
Building Site:
- ProSteel – Installing Partition Steel at Level 3 Restrooms
- Pan Pacific – In-Wall Rough at All Levels.
- Masonry Concepts – Scaffolding Dismantle at West Side
- Pacific Coast Glazing – Level 5 East Glazing
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of February 20th through February 25th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Curtain Wall Framing & Glazing at all levels. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium-level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Pour Oak Grove Ramp Footings. (Equipment: Various hand and power tools).
- Please be advised on Thursday*, 02/23 we will be placing concrete. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open at all times and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
-
954045 SOM ED II Construction Alert #87
02/13/2023-02/18/2023
954045 SOM ED II Construction Alert #87
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, February 11th.
Building Site:
- AO Reed – Level 3 Duct Work
- Masonry Concepts – West Brick Installation
- Pacific Coast Glazing – Level 5 NorthEast CW Glazing
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of February 13th through February 18th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Finish Level 3 Roof PVC. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Curtain Wall Framing & Glazing at all levels. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium-level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Pour Oak Grove Ramp Footings. (Equipment: Various hand and power tools).
- Please be advised on Friday, 02/17 we will be placing concrete. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open at all times and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
-
954045 SOM ED II - Construction Alert #86
02/04/2023-02/11/2023
954045 SOM ED II Construction Alert #86
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, February 04th.
Building Site:
· SDI – Elevator Fronts
- AO Reed – Level 2 Duct Work
- Masonry Concepts – South Scaffolding Erection
- Pacific Coast Glazing – Level 5 North CW Framing
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of February 6th through February 11th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Finish Level 3 Roof PVC activities. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Curtain Wall Framing & Glazing at all levels. (Equipment: Various hand and power tools).
- Pour Loading Dock Ramp. (Equipment: Various hand and power tools).
- Please be advised on Wednesday 02/08 we will be placing concrete and access to the loading dock will not be available from 6:00 AM – 7:00 AM. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Anticipated disturbances: Medium-level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Accessibility to the loading dock will not be available on Wednesday 02/08 from 6:00 AM – 7:00 AM.
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open at all other times and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
-
954045 SOM ED II - Construction Alert #85
01/28/2023-02/04/2023
954045 SOM ED II Construction Alert #85
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, January 28th.
Building Site:
· SDI – Level 2 Drywall & Taping
- AO Reed – Roof Duct Work
- AVI – Run cabling at Level 2 South Drop Soffit
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of January 30th through February 04th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Start Level 3 Roof PVC activities. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Curtain Wall Framing at all levels. (Equipment: Various hand and power tools).
- Continue Curtain Wall Glazing at all levels. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium-level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Landscaping Exploratory Work & Irrigation Main Installation. (Equipment: Various hand and power tools).
- There will be no disruptions to the loading dock activities.
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
-
954045 SOM ED II - Construction Alert #84
01/21/2023-01/28/2023
954045 SOM ED II Construction Alert #84
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, January 21st.
Building Site:
· CSI – Temporary Power Shut Down limited to project site (No impact to other buildings) for Generator EDII & Oak Grove Ramp Electrical Work
- PCG – Level 5 South Glazing Installation
- AO Reed – Level 4 Duct Work
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of January 23rd through January 28th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Tower Crane Pad Demo. (Equipment: Various hand and power tools).
- Anticipated disturbances: High-level construction noise and vibration on Building Site.
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Continue Roof PolyISO, Roof Board & PVC activities. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Curtain Wall Framing at all levels. (Equipment: Various hand and power tools).
- Continue Curtain Wall Glazing at all levels. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium-level construction noise and vibration on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Landscaping Exploratory Work & Irrigation Main Installation. (Equipment: Various hand and power tools).
- There will be no disruptions to the loading dock activities.
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #83
01/15/2023-01/21/2023
954045 SOM ED II Construction Alert #83
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, January 14th.
Building Site:
· Level 5 Ductwork – AO Reed
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of January 09th through January 14th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick & Mortar. (Equipment: Various hand and power tools).
- Continue Roof PolyISO, Roof Board & PVC activities. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Curtainwall Framing at all levels. (Equipment: Various hand and power tools).
- Continue Curtain Wall Glazing at all levels. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium-level construction noise and vibration on Building Site.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
-
954045 SOM ED II Construction Alert #82
01/07/2023-01/14/2023
954045 SOM ED II Construction Alert #82
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, January 7th & Sunday, January 8th.
Building Site:
· Tower Crane Removal – Cab, Slew ring, and base sections removal. (Saturday)
- Tower Crane Removal – 500T dismantle and removal from the project. (Sunday)
- See attached 500-Ton Path of Travel.
- Anticipated disturbances: Medium-level construction noise on Building Site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of January 09th through January 14th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Tower Crane Pad Demo. (Equipment: Various hand and power tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Level 1 Exterior Brick & Start Level 2 South Brick. (Equipment: Various hand and power tools).
- Continue Roof PolyISO, Roof Board & PVC activities. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Curtainwall Framing at all levels. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium-level construction noise and vibration on Building Site.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Pour Fence Post Bases. (Equipment: Various hand and power tools).
- Please be advised on Friday 01/13 we will be placing concrete. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
- Tower Crane Removal – 500T dismantle and removal from the project. (Sunday)
-
954045 SOM ED II - Construction Alert #81
01/01/2023-01/07/2023
954045 SOM ED II Construction Alert #81
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of January 02nd through January 07th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Level 1 Exterior Brick & Start Level 2 South Brick. (Equipment: Various hand and power tools).
- Continue Roof PolyISO, Roof Board & PVC activities. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Curtainwall Framing at all levels. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Pour Fence Post Bases. (Equipment: Various hand and power tools).
- Please be advised on Friday 01/06 we will be placing concrete. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #80
12/24/2022-12/31/2022
954045 SOM ED II Construction Alert #80
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of December 26th through December 31st. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Level 1 Exterior Brick. (Equipment: Various hand and power tools).
- Continue Roof PolyISO, Roof Board & PVC activities. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Curtainwall Framing at all levels. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Backfill Retaining Walls
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #79
954045 SOM ED II Construction Alert #79
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, December 17th.
Building Site:
· Level 3-5 Running Duct. (Equipment: Various hand and power tools).
- Continuing Storm Drain run. (Equipment: Various hand and power tools).
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of December 19th through December 24th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue Interior build-out. (Equipment: Various hand and power tools).
- Pour L2 Oculus Curb. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Level 1 Exterior Brick. (Equipment: Various hand and power tools).
- Begin Roof PolyISO. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Level 4-5 Curtainwall Framing. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #78
954045 SOM ED II Construction Alert #78
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of December 10th through December 15th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue erecting Roof Mechanical Screen & PV Array steel structure. (Equipment: Tower crane, various hand tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Level 1 Exterior Brick. (Equipment: Various hand and power tools).
- Continue Roof PolyISO. (Equipment: Various hand and power tools).
- Begin curtain wall glazing. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Level 2 Curtainwall Framing. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #77
954045 SOM ED II Construction Alert #77
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, December 3rd.
Building Site:
· Level 2 – Overhead Duct. (Equipment: Various hand and power tools).
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of December 05th through December 10th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue erecting Roof Mechanical Screen & PV Array steel structure. (Equipment: Tower crane, various hand tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Level 1 Exterior Brick. (Equipment: Various hand and power tools).
- Begin Roof PolyISO. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Continue Level 2 Curtainwall Framing. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium level construction noise on Building Site
New Generator Yard:
- Pour Oak Grove Ramp Footings, Retaining Wall Footings & SOG inside the Generator Yard. (Equipment: Various hand and power tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
Anticipated disturbances: Low level construction noise contained to surrounding area.
Please be advised on Monday December 05th there will be a concrete placement. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #76
954045 SOM ED II Construction Alert #76
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of November 28th through December 03rd. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue Roof Penthouse Metal Decking. (Equipment: Tower crane, various hand tools).
- Pour Stair 8. (Equipment: Various hand and power tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick Anchor Layout. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Start Curtainwall Framing. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Site.
Please be advised on Monday November 28th concrete placement will continue. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
New Generator Yard:
· Grading at Oak Grove Ramp
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #75
954045 SOM ED II Construction Alert #75
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of November 21st through November 26th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue steel erection for Roof Penthouse & Oculus. (Equipment: Tower crane, various hand tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue Exterior Brick Anchor Layout. (Equipment: Various hand and power tools).
- Continue Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Site.
Please be advised on Monday November 21st concrete placement will continue. Anticipated timeline 7AM – 9AM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
New Generator Yard:
· Grading at Oak Grove Ramp
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #74
954045 SOM ED II Construction Alert #74
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of November 14th through November 18th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue steel erection for Roof Penthouse & Oculus. (Equipment: Tower crane, various hand tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Begin Exterior Brick Anchor Layout. (Equipment: Various hand and power tools).
- Begin Exterior HT Membrane & SS flashings. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Sites
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #73
954045 SOM ED II Construction Alert #73
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, November 5th.
Building Site:
- Roof Mastic Application. (Equipment: Various hand and power tools).
- Elevator Shaft Framing. (Equipment: Various hand and power tools).
- Storm Drain Tie-In at the East Side. (Equipment: Various hand and power tools).
- HP to be onsite for rain preparation. (Equipment: Various hand and power tools).
· Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of November 07th through November 11th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue steel erection for Roof Penthouse. (Equipment: Tower crane, various hand tools).
- Pour Level 2 Stairs 8 and Ramp.
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue exterior framing on Level 5 (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-5. (Equipment: Various hand and power tools).
- Continue scaffold activities on the North side. (Equipment: Various hand and power tools).
- Continue roof mastic application. (Equipment: Various hand and power tools).
Anticipated disturbances: Medium level construction noise on Building Site.
Please be advised on Wednesday November 09th concrete placement will continue. Anticipated timeline 7AM – 9AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #72
954045 SOM ED II Construction Alert #72
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of October 31st through November 04th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue steel erection of exterior skin on Level 2. (Equipment: Tower crane, various hand tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue exterior framing on Level 5 (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-4. (Equipment: Various hand and power tools).
- Continue scaffold activities on the South side. (Equipment: Various hand and power tools).
- Continue roof vapor Barrier install. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Site
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #71
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of October 24th through October 28th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Pour Level 2 infill and ramp. (Equipment: Tower crane, various hand tools).
- Continue steel erection of exterior skin on Level 1 & Level 2. (Equipment: Tower crane, various hand tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue exterior framing on Levels 3 & 4. (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-4. (Equipment: Various hand and power tools).
- Begin scaffold activities on the South side. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Site.
Please be advised that concrete placement will continue Monday October 24th . Anticipated timeline 9AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #70
954045 SOM ED II Construction Alert #70
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of October 17th through October 21st. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue pouring Stair 4 landings (L5-6). (Equipment: Tower crane, various hand tools).
- Continue steel erection at Oculus on Level 2 & 3 and Elevator Shaft. (Equipment: Tower crane, various hand tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Begin Scaffolding at South side (Equipment: Various hand and power tools).
- Continue exterior framing on Levels 1, 2 & 3. (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-4. (Equipment: Various hand and power tools).
- Continue backfill & waterproofing operations at South Fire Road
- Anticipated disturbances: Medium level construction noise on Building Site.
Please be advised that concrete placement will continue Wednesday October 19th. Anticipated timeline 9AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #69
954045 SOM ED II Construction Alert #69
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of October 10th through October 14th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
· Continue pouring Stair 4 landings. (Equipment: Tower crane, various hand tools).
- Continue steel erection of exterior skin on Level 1 & Level 2. (Equipment: Tower crane, various hand tools).
- Continue pouring Roof Parapet walls. (Equipment: various hand tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue exterior framing on Levels 1 & 2. (Equipment: Various hand and power tools).
- Continue MEP activities on Levels 1-4. (Equipment: Various hand and power tools).
- Continue backfill & waterproofing operations at South Fire Road
- Anticipated disturbances: Medium level construction noise on Building Site.
Please be advised that concrete placement will continue Wednesday October 12th and Thursday October 13th. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #68
954045 SOM ED II Construction Alert #68
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of October 03rd through October 07th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue installing shoring for Stair 4. (Equipment: Tower crane, various hand tools).
- Continue steel erection of exterior skin on Level 1 & Level 2. (Equipment: Tower crane, various hand tools).
- Continue curb layout on Levels 2-4. (Equipment: Tower crane, various hand tools).
- Pour Level 5 Exterior Curbs & Level 1 Planter Wall (Northwest Side). (Equipment: various hand tools).
- Domestic & Fire Water Tie-In at South Fire Access Road. (Equipment: Various hand and power tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Continue MEP activities on Level 1-4.
- Anticipated disturbances: Medium level construction noise on Building Site.
Please be advised that concrete placement will continue on Wednesday October 05th. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Continue unloading dirt at Generator Yard to support the backfill activity by the Greenhouses
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #67
954045 SOM ED II Construction Alert #67
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of September 26th through September 30th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue installing shoring for Stair 4. (Equipment: Tower crane, various hand tools).
- Continue steel erection of exterior skin on Level 1. (Equipment: Tower crane, various hand tools).
- Continue curb layout on Levels 2-4. (Equipment: Tower crane, various hand tools).
- Pour Level 3 Exterior Curbs. (Equipment: various hand tools).
- Domestic & Fire Water Tie-In at South Fire Access Road. (Equipment: Various hand and power tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Site.
Please be advised that concrete placement will continue on Tuesday September 27th. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #66
954045 SOM ED II Construction Alert #66
Please be advised that the following activities will be occurring from 5:00AM to 3:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, September 17th.
Building Site:
· Man Hoist Build Out to Level 6. (Equipment: Tower crane, various hand tools
· Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of September 19th through September 23rd. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue installing shoring for Stair 4. (Equipment: Tower crane, various hand tools).
- Continue steel erection of exterior skin on Level 1. (Equipment: Tower crane, various hand tools).
- Continue curb layout on Levels 2-4. (Equipment: Tower crane, various hand tools).
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Site.
New Generator Yard:
- Continue Metal Panel Installation.
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #65
954045 SOM ED II Construction Alert #65
Please be advised that the following activities will be occurring from 5:00AM to 3:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, September 10th.
Building Site:
· Continue rebar of Level 6 East Deck. (Equipment: Tower crane, various hand tools).
· Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of September 12th through September 16th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue installing shoring for Stair 4. (Equipment: Tower crane, various hand tools).
- Continue steel erection of exterior skin on Level 1. (Equipment: Tower crane, various hand tools).
- Continue curb layout on Levels 2-3. (Equipment: Tower crane, various hand tools).
- Continue rebar of Level 6 East Deck
- Continue Interior build-out. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Site.
- Please be advised that concrete placement will continue on Tuesday September 13th. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Continue Metal Panel Installation.
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #64
954045 SOM ED II Construction Alert #64
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of September 6th through September 9th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue steel erection of exterior skin. (Equipment: Tower crane, various hand tools).
- Continue decking of Level 6 East Deck. (Equipment: Tower crane, various hand tools).
- Continue MEPF and rebar setting for Level 6 Deck. (Equipment: Tower crane, various hand tools).
- Continue building of stairs mid-landings. (Equipment: Tower crane, various hand tools).
- Continue Interior build out. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Site.
- Please be advised that concrete placement will continue on Wednesday September 07th. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- No activities scheduled for New Generator Yard.
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #63
954045 SOM ED II Construction Alert #63
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of August 29th through September 02nd. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue steel erection of exterior skin. (Equipment: Tower crane, various hand tools).
- Continue decking of Level 6 East Deck. (Equipment: Tower crane, various hand tools).
- Start MEPF and rebar setting for Level 6 Deck. (Equipment: Tower crane, various hand tools).
- Continue building of stairs mid-landings. (Equipment: Tower crane, various hand tools).
- Continue Interior build out. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise on Building Site.
- Please be advised that concrete placement will continue on Wednesday August 31st. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- No activities scheduled for New Generator Yard.
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathwaysand the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #63
954045 SOM ED II Construction Alert #62
Please be advised that the following activities will be occurring from 5:00AM to 2:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, August 20th.
Building Site:
- Completion of stressing the remainder of the floors PT (Equipment: Various hand tools).
- Continue rebar of Level 6 West Deck. (Equipment: Tower crane, various hand tools).
- Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of August 22nd through August 26th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue rebar of Level 6 West Deck. (Equipment: Tower crane, various hand tools).
- Continue steel erection of exterior skin. (Equipment: Tower crane, various hand tools).
- Continue decking of Level 6 East Deck. (Equipment: Tower crane, various hand tools).
- Continue Interior build out. (Equipment: Various hand and power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that concrete placement will continue on Wednesday August 24th. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- No activities scheduled for New Generator Yard.
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathwaysand the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #61
954045 SOM ED II Construction Alert #61
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of August 15th through August 20th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue setting of Level 6 Deck. (Equipment: Tower crane, various hand tools).
- Rebar and Mechanical Inserts on Level 6 East (Equipment: Tower crane, various hand tools).
- Various Level 1 and Level 2 Curbs forming, rebar and placing (Equipment: Various hand tools).
- Backfill to grade (Equipment: Various mechanical equipment).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
New Generator Yard:
- No activities scheduled for New Generator Yard.
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathwaysand the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #60
954045 SOM ED II Construction Alert #60
Please be advised that the following activities will be occurring from 5:00AM to 2:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, August 06th.
Building Site:
- Continue rebar and forming of Level 5 West Verticals. (Equipment: Tower Crane, Various Hand Tools).
- Stripping of Level 5 West Deck. (Equipment: Tower Crane, Various Hand Tools).
- Continue Level 6 East Deck (Equipment: Tower Crane, Various hand tools).
- Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of August 08th through August 12th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue rebar and forming of Level 5 West verticals. (Equipment: Tower crane, various hand tools).
- Continue setting of Level 6 Deck. (Equipment: Tower crane, various hand tools).
- Rebar and Mechanical Inserts on Level 6 East (Equipment: Tower crane, various hand tools).
- Various Level 1 and Level 2 Curbs forming, rebar and placing (Equipment: Various hand tools).
- Backfill to grade (Equipment: Various mechanical equipment).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue Monday August 08th, Tuesday August 09th and Friday August 12th Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathwaysand the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
- Continue rebar and forming of Level 5 West Verticals. (Equipment: Tower Crane, Various Hand Tools).
-
954045 SOM ED II - Construction Alert #59
954045 SOM ED II Construction Alert #59
Please be advised that the following activities will be occurring from 5:00AM to 2:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, July 30th.
Building Site:
- Mechanical Inserts on Level 5 West Deck (Equipment: Various hand tools).
- Stripping of Level 5 East Deck (Equipment: Tower Crane, Various Hand Tools).
- Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of August 01st through August 05th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Start wall fabrication of level 5 East. (Equipment: Tower crane, forklift, various hand power tools).
- Start work on level 5 vertical reinforcement. (Equipment: Tower crane, various hand tools).
- Continue setting of Level 5 deck. (Equipment: Tower crane, various hand tools).
- Rebar and Mechanical Inserts on Level 5 West Deck. (Equipment: Tower crane, various hand tools).
- Continue work on level 5 West vertical reinforcement. (Equipment: Tower crane, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue Wednesday August 03rd and Friday August 05th, Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Low level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Low level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #58
954045 SOM ED II Construction Alert #58
Please be advised that the following activities will be occurring from 5:00AM to 2:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, July 23rd.
Building Site:
- Stressing of Level 4 West Deck (Equipment: Various hand tools).
- Continue rebar of Level 5 East Verticals (Equipment: Tower Crane, Various hand tools).
- Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of July 25th through July 29th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue wall fabrication of level 4 West. (Equipment: Tower crane, forklift, various hand power tools).
- Continue work on level 4 vertical reinforcement. (Equipment: Tower crane, various hand tools).
- Continue setting of Level 5 deck. (Equipment: Tower crane, various hand tools).
- Rebar and Mechanical Inserts on Level 5 East Deck. (Equipment: Tower crane, various hand tools).
- Continue work on level 5 east vertical reinforcement. (Equipment: Tower crane, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue Monday July 25th, Tuesday July 26th, and Friday July 29th, Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- FRP gravity curb (Equipment: Various hand power tools, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
- Please be advised of concrete placement on Tuesday July 26th. Anticipated timeline 11AM – 1PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #57
954045 SOM ED II Construction Alert #57
Please be advised that the following activities will be occurring from 5:00AM to 2:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, July 22nd.
Building Site:
- Continue rebar on level 4 deck (Equipment: Tower Crane, various hand tools).
- Continue MEP inserts on level 4 deck (Equipment: Various hand tools).
- Instillation of generator at Generator Yard (Equipment: Tower Crane, Delivery Trucks). (See attached exhibit for Lot 11 Crane set up and parking)
- Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of July 18th through July 22nd The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue rebar of level 4 West deck (Equipment: Tower crane, various hand tools).
- Setting level 4 walls and column forms (Equipment: Tower crane, various hand tools).
- Continue work on level 4 vertical reinforcement (Equipment: Tower crane, various hand tools).
- Continue work on level 4 deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower crane, forklift, various hand power tools).
- Setting Level 5 deck (Equipment: Tower crane, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue Wednesday July 20th and Thursday July 21st, Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- FRP gravity curb (Equipment: Various hand power tools, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #56
954045 SOM ED II Construction Alert #56
Please be advised that the following activities will be occurring from 5:00AM to 2:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, July 16th.
Building Site:
- Continue strip of level 4 east deck and rebar of level 4 west deck (Equipment: Tower Crane, various hand tools).
- Continue work on Level 4 vertical west rebar (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of July 11th through July 15th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue rebar of level 4 West deck (Equipment: Tower crane, various hand tools).
- Setting level 4 walls and column forms (Equipment: Tower crane, various hand tools).
- Continue work on level 4 vertical reinforcement (Equipment: Tower crane, various hand tools).
- Continue work on level 4 deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower crane, forklift, various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue Tuesday July 12th and Friday July 15th, Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- FRP gravity curb (Equipment: Various hand power tools, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #55
954045 SOM ED II Construction Alert #55
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of July 05th through July 09th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue rebar of level 4 East deck (Equipment: Tower crane, various hand tools).
- Setting level 4 walls and column forms (Equipment: Tower crane, various hand tools).
- Continue work on level 4 vertical reinforcement (Equipment: Tower crane, various hand tools).
- Continue work on level 4 deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower crane, forklift, various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue Tuesday July 05th and Friday July 08th, Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- FRP gravity curb (Equipment: Various hand power tools, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- No activities scheduled for Headhouse 7
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #52
954045 SOM ED II Construction Alert #52
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, June 11th:
Building Site:
- Continue setting wall panels on level 2 deck (Equipment: Tower Crane, various hand tools).
- Continue sheeting level 3 deck (Equipment: Scissor lift, various hand tools).
- Continue rebar on level 3 deck (Equipment: Tower Crane, various hand tools).
- Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of June 13th through June 18th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Setting level 3 walls and column forms (Equipment: Tower crane, various hand tools).
- Continue work on level 3 vertical reinforcement (Equipment: Tower crane, various hand tools).
- Continue work on level 3 deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower crane, forklift, various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue Monday June 13th and Thursday June 16th. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- FRP gravity curb (Equipment: Various hand power tools, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue GC punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #54
954045 SOM ED II Construction Alert #54
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, June 25th:
Building Site:
- Setting vertical formwork on level 3 (Equipment: Tower crane, various hand tools).
- Stripping level 3 deck (Equipment: Scissor lift, various hand tools).
- Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of June 27th through July 02nd. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Setting level 3 walls and column forms (Equipment: Tower crane, various hand tools).
- Continue work on level 3 vertical reinforcement (Equipment: Tower crane, various hand tools).
- Continue setting level 4 East deck (Equipment: Tower crane, various hand tools).
- Begin rebar of level 4 East deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower crane, forklift, various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue Monday June 27h and Thursday June 30th, Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Setting of 200 kW generator (Equipment: Mobile crane, various hand tools).
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- FRP gravity curb (Equipment: Various hand power tools, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
- Please be advised on Thursday June 30th, we will have a mobile crane set up along the North side of Parking Lot 11. Please see the attached exhibit for reference.
Headhouse 7:
- Continue GC punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #53
954045 SOM ED II Construction Alert #53
Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, June 18th:
Building Site:
- Continue rebar on level 3 vertical (Equipment: Various hand tools).
- Stressing of level 3 East deck (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of June 20th through June 25th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Setting level 3 walls and column forms (Equipment: Tower crane, various hand tools).
- Continue work on level 3 vertical reinforcement (Equipment: Tower crane, various hand tools).
- Continue rebar of level 3 deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower crane, forklift, various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue Monday June 20th , Thursday June 23rd, and Friday June 24th. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- FRP gravity curb (Equipment: Various hand power tools, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue GC punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #51
954045 SOM ED II Construction Alert #51
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, June 4th:
Building Site:
- Continue stripping wall panels on level 2 deck (Equipment: Tower Crane, various hand tools).
- Continue setting wall panels on level 2 deck (Equipment: Tower Crane, various hand tools).
- Continue stripping underside of level 2 East deck (Equipment: Scissor lift, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of June 6th through June 11th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue setting level 2 walls and column forms (Equipment: Tower crane, various hand tools).
- Continue stripping level 2 walls and column forms (Equipment: Tower crane, various hand tools).
- Continue work on level 2 vertical reinforcement (Equipment: Tower crane, various hand tools).
- Continue setting level 3 deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower crane, forklift, various hand power tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue on Monday June 6th and Thursday June 9th. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- FRP gravity curb (Equipment: Various hand power tools, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue GC punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #50
954045 SOM ED II Construction Alert #50
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, May 28th:
Building Site:
- Patching of PT tendons on South end of building (Equipment: Scissor lift, various hand tools).
- Continue setting wall panels on level 2 deck (Equipment: Tower Crane, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of May 31st through June 4th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue rebar of level 2 loading dock deck (Equipment: Tower crane, various hand tools).
- Continue setting level 2 walls and column forms (Equipment: Tower crane, various hand tools).
- Continue work on level 2 vertical reinforcement (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower Crane, forklift, various hand power tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue on Wednesday, Thursday, and Friday - June 1st through June 3rd. Anticipated timeline 3AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin setting enclosure metal panels (Equipment: Delivery truck, forklift, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue GC punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #48
954045 SOM ED II Construction Alert #48
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, May 14th:
Building Site:
- Continue level 2 West deck MEP layout (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of May 16th through May 21st. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Begin rebar of level 2 West deck (Equipment: Tower crane, various hand tools).
- Continue work on level 2 East deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower Crane, forklift, various hand power tools).
- Continue loading dock slab on grade activities (Equipment: Mini-ex, forklift, various hand power tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue on Tuesday, May 17th. Anticipated timeline 3AM – 10AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Continue erection of new generator yard enclosure (Equipment: Generator, impact guns, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue GC punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
- Please see attached notification from Facilities for the proposed electrical power service interruption at Greenhouse and Headhouse #7 scheduled for Tuesday, May 24th.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #47
954045 SOM ED II Construction Alert #47
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, May 7th:
Building Site:
- Continue setting level 2 West deck formwork (Equipment: Tower crane, various hand tools).
- Continue work on level 2 East deck (Equipment: Tower crane, various hand power tools).
- Continue backfill operation at loading dock (Equipment: Skid Steer, Roller and various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of May 9th through May 14th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue forming level 2 West deck (Equipment: Tower crane, various hand tools).
- Continue work on level 2 East deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower Crane, forklift, various hand power tools).
- Continue loading dock slab on grade activities (Equipment: Mini-ex, forklift, various hand power tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue on Thursday, May 12th. Anticipated timeline 10AM – 1PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Continue erection of new generator yard enclosure (Equipment: Generator, impact guns, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue GC punch list (Equipment: Various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #46
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, April 30th:
Building Site:
- Continue setting level 2 East deck formwork (Equipment: Tower crane, various hand tools).
- Continue prepping for Slab on Grade(SOG) West (Equipment: Skid steer, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of May 2nd through May 7th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue forming level 2 deck (Equipment: Tower crane, various hand tools).
- Continue wall panel fabrication (Equipment: Tower Crane, forklift, various hand power tools).
- Continue slab on grade (SOG) activities (Equipment: Mini-ex, forklift, various hand power tools).
- Continue backfill at SOG (Equipment: Mini-ex, skid steer, whacker and various hand tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue on Wednesday, May 4th. Anticipated timeline 4AM – 11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
- Please be advised Monday, May 2nd from 5:00AM to 7:00AM a crane will be setup in the West Courtyard. Access to the temporary loading dock will be unavailable during this activity. Please reference Alternative Crane Pick Location exhibit.
New Generator Yard:
- Begin painting HSS steel (Equipment: Generator, paint sprayer, various hand tools, respiratory masks).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue interior finishes (Equipment: Delivery trucks, ladders, various hand power tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
- Please be advised Monday, May 2nd from 5:00AM to 7:00AM a crane will be setup in the West Courtyard. Access to the temporary loading dock will be unavailable during this activity. Please reference Alternative Crane Pick Location exhibit.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #45
954045 SOM ED II Construction Alert #45
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, April 23rd:
Building Site:
- Continue setting level 2 East deck formwork (Equipment: Tower crane, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of April 25th through April 30th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue placing level 1 walls & columns (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Continue wall panel fabrication (Equipment: Tower Crane, forklift, various hand power tools).
- Continue rebar of level 1 vertical (Equipment: Delivery trucks, crane, various hand tools).
- Continue slab on grade(SOG) activities (Equipment: Mini-ex, forklift, various hand power tools).
- Continue backfill at SOG (Equipment: Mini-ex, skid steer, whacker and various hand tools).
- Continue forming level 2 deck (Equipment: Tower crane, various hand tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue on Wednesday, April 27th and Thursday, April 28th. Anticipated timeline 4AM – 11 AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin painting HSS steel (Equipment: Generator, paint sprayer, various hand tools, respiratory masks).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Begin interior finishes (Equipment: Delivery trucks, ladders, various hand power tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
- Please be advised Monday, May 2nd from 5:00AM to 7:00AM a crane will be setup in the West Courtyard. Access to the temporary loading dock will be unavailable during this activity. Please reference Alternative Crane Pick Location exhibit.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project
-
954045 SOM ED II Construction Alert #44
954045 SOM ED II Construction Alert #44
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, April 16th:
Building Site:
- Continue vapor barrier on slab on grade East (Equipment: various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of April 18th through April 23rd. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue placing level 1 walls & columns (Equipment: Concrete trucks, concrete pumps, light towers, concrete finishing tools & various hand tools).
- Continue wall fabrication (Equipment: Tower Crane, forklift, various hand power tools).
- Continue rebar of level 1 vertical (Equipment: Delivery trucks, crane, various hand tools).
- Continue slab on grade activities (Equipment: Mini-ex, forklift, various hand power tools).
- Continue backfill at slab on grade (Equipment: Mini-ex, skid steer, whacker and various hand tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement will continue on Monday, April 18th and Thursday, April 21st. Anticipated timeline 4AM – 11 AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin painting HSS steel (Equipment: Generator, paint sprayer, various hand tools, respiratory masks).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Begin interior finishes (Equipment: Delivery trucks, ladders, various hand power tools).
- Begin flooring (Equipment: Delivery trucks, floor material, various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
- Please be advised Friday, April 22nd from 5:00AM to 6:30AM a crane will be setup in the West Courtyard. Access to the temporary loading dock will be unavailable during this activity. Please reference Alternative Crane Pick Location exhibit.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #43
954045 SOM ED II Construction Alert #43
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, April 9th:
Building Site:
- Continue setting wall panels and forming level 1 vertical (Equipment: Tower crane, various hand tools).
- Continue install of underground utilities at slab on grade (Equipment: Mini excavator, various hand tools).
- Continue backfill of underground utilities (Equipment: Skid steer, mini excavator, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of April 11th through April 16th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue placing level 1 walls & columns (Equipment: Concrete trucks, concrete pumps, light towers, concrete finishing tools & various hand tools).
- Continue wall fabrication (Equipment: Tower Crane, forklift, various hand power tools).
- Continue rebar of level 1 vertical (Equipment: Delivery trucks, crane, various hand tools).
- Continue slab on grade underground activities (Equipment: Mini-ex, forklift, various hand power tools).
- Continue backfill at slab on grade (Equipment: Mini-ex, skid steer, whacker and various hand tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement for walls will continue on Monday, April 11 and Wednesday, April 13. Anticipated timeline 4AM – 11 AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin painting HSS steel (Equipment: Generator, paint sprayer, various hand tools, respiratory masks).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Begin interior finishes (Equipment: Delivery trucks, ladders, various hand power tools).
- Begin flooring (Equipment: Delivery trucks, floor material, various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #42
954045 SOM ED II Construction Alert #42
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, April 2nd:
Building Site:
- Continue rebar install in foundation (Equipment: Tower crane, various hand tools).
- Continue setting wall panels and forming foundation (Equipment: Tower crane, various hand tools).
- Continue install of underground utilities at slab on grade East (Equipment: Mini excavator, various hand tools).
- Continue backfill of slab on grade West (Equipment: Skid steer, mini excavator, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of April 4th through April 9th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue placing level 1 walls & columns (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Continue wall fabrication (Equipment: Tower Crane, forklift, various hand power tools).
- Continue rebar of foundation placement #4 (Equipment: Delivery trucks, crane, various hand tools).
- Continue slab on grade underground activities (Equipment: Mini-ex, forklift, various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the concrete placement for walls and foundations will continue on Monday April 4, Tuesday April 5, and Thursday April 7. Anticipated timeline 4AM – 11 AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin painting HSS steel (Equipment: Generator, paint sprayer, various hand tools, respiratory masks).
- Begin grading generator yard (Equipment: Skid steer, mini excavator, various hand tools).
- Begin gate hardware installation (Equipment: Delivery truck, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue painting interior (Equipment: Ladders, various hand tools).
- Begin interior finishes (Equipment: Delivery trucks, ladders, various hand power tools).
- Begin flooring (Equipment: Delivery trucks, floor material, various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
- Please see attached notification from Facilities for the planned steam shutdown anticipated for April 5th at HH/GH 7-14.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #41
954045 SOM ED II Construction Alert #41
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, March 26th:
Building Site:
- Stripping/Chipping walls (Equipment: 350 ton crane, forklift, chipping gun and various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of March 28th through April 2nd. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue placing level 1 walls & columns (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Continue wall fabrication (Equipment: 350 ton Crane, Tower Crane, forklift, various hand power tools).
- Begin rebar of foundation placement #4 (Equipment: Delivery trucks, crane, various hand tools).
- Continue slab on grade underground activities (Equipment: Mini-ex, forklift, various hand power tools).
- Removal of 350 Ton mobile crane (Equipment: Delivery trucks, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised on Thursday, March 31, a wall & column placement of approximately 130 CY will occur. Anticipated timeline 4AM – 11 AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Continue installing enclosure structural steel (Equipment: Delivery trucks, concrete trucks, forklift, various hand and power tools).
- Begin painting HSS steel (Equipment: Generator, paint sprayer, various hand tools, respiratory masks).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Begin interior finishes (Equipment: Delivery trucks, ladders, various hand power tools).
- Begin flooring (Equipment: Delivery trucks, floor material, various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #40
954045 SOM ED II Construction Alert #40
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, March 19th:
Building Site:
- Stripping/Chipping walls (Equipment: 350 ton crane, forklift, chipping gun and various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of March 21st through March 26th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue placing level 1 walls & columns (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Continue wall fabrication (Equipment: 350 ton Crane, forklift, various hand power tools).
- Begin excavation of foundation placement #4 (Equipment: Excavator, loader, various hand tools).
- Begin slab on grade underground activities (Equipment: Mini-ex, forklift, various hand power tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the soil export activities will be continuing throughout next week. Soil haul trucks will be present on site and transiting the adjacent areas intermittently throughout the week to support these activities. Please reference Soil Export Traffic Control Plan exhibit.
- Please be advised on Friday, March 25th, a wall concrete placement of approximately 130 CY will occur. Anticipated timeline 4AM-11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Continue installing enclosure structural steel (Equipment: delivery trucks, concrete trucks, forklift, various hand and power tools).
- Begin excavating chain link fence footings (Equipment: delivery trucks, hydrovac trucks, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue roofing connection (Equipment: ladders, power tools, and various hand tools).
- Continue drywall (Equipment: ladders, power tools and various hand tools).
- Begin interior finishes (Equipment: Delivery trucks, ladders, various hand power tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #39
954045 SOM ED II Construction Alert #39
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, March 12th:
Building Site:
- Stripping/Chipping walls (Equipment: 350 ton crane, forklift, chipping gun and various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of March 14th through March 19th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Tower crane erection (Equipment: Delivery trucks, 350 ton support crane, various rigging equipment).
- Continue placing level 1 walls & columns (Equipment: concrete trucks, concrete pumps, light towers, concrete finishing tools & various hand tools).
- Continue wall fabrication (Equipment: 350 ton crane, forklift, various hand power tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised on Thursday, March 17th, a wall concrete placement of approximately 170 CY will occur. Anticipated timeline 4AM-11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Continue installing enclosure structural steel (Equipment: delivery trucks, concrete trucks, forklift, various hand and power tools).
- Begin excavating chain link fence footings (Equipment: delivery trucks, hydrovac trucks, various hand tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Begin roofing connection (Equipment: ladders, power tools, and various hand tools).
- Begin drywall. (Equipment: ladders, power tools and various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
- Please be advised on Thursday, March 17th, a wall concrete placement of approximately 170 CY will occur. Anticipated timeline 4AM-11AM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #38
954045 SOM ED II Construction Alert #38
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, March 5th:
Building Site:
- Stripping walls (Equipment: 350 ton Crane, forklift, various hand power tools).
- Placing trench plates (Equipment: Delivery truck, forklift, various hand power tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of March 7th through March 12th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Wall Placement #2 (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Delivery and mobilization of 500 ton crane anticipated early AM on Monday March 7th (Equipment: 350 ton crane & support trucks).
- Tower crane erection (Equipment: 350 and 500 ton cranes & support trucks).
- Continue wall fabrication (Equipment: 350 ton Crane, forklift, various hand power tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised on Friday, March 11th, the second wall concrete placements of approximately 400 CY will occur. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Continue installing the enclosure structural steel (Equipment: Delivery trucks, concrete trucks, forklift, various hand and power tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue exterior lath and plaster (Equipment: Mixer, ladders, air compressor, staple gun and various hand tools).
- Begin roofing activities (Equipment: Air compressor, and various hand tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
- Please be advised on Friday, March 11th, the second wall concrete placements of approximately 400 CY will occur. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: Delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: Delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #37
954045 SOM ED II Construction Alert #37
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, February 26th:
Building Site:
- Continue rebar for foundation (Equipment: 350 ton Crane, delivery trucks, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of February 28th through March 5th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue rebar for foundation placement #2 & #3 (Equipment: 350 ton Crane, delivery trucks, various hand tools).
- Foundation Placement #2 (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Foundation Placement #3 (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Wall Placement #1 (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Wall Placement #2 (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Continue wall fabrication (Equipment: 350 ton Crane, forklift, various hand power tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that the soil export activities will be continuing throughout next week. Soil haul trucks will be present on site and transiting the adjacent areas intermittently throughout the week to support these activities. Please reference Soil Export Traffic Control Plan exhibit.
- Please be advised on Wednesday, March 2nd, the first Wall concrete placement of approximately 100 CY will occur. Anticipated timeline 12PM-4PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
- Please be advised on Thursday, March 3rd, the second foundation concrete placement of approximately 600 CY will occur. Anticipated timeline 4AM-1PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
- Please be advised on Friday, March 4th, the third foundation & second wall concrete placements of approximately 400 CY will occur. Anticipated timeline 5AM-4PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Continue installing the enclosure structural steel. (Equipment: Delivery trucks, concrete trucks, forklift, various hand and power tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
- Please see attached reminder notification from Facilities for the planned electrical power service interruption scheduled for March 1st.
Headhouse 7:
- Continue framing walls for the new headhouse (Equipment: Delivery truck, various hand power tools).
- Begin exterior lath and plaster. (Equipment: Mixer, ladders, air compressor, staple gun and various hand tools.)
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
- Please be advised on Wednesday, March 2nd, the first Wall concrete placement of approximately 100 CY will occur. Anticipated timeline 12PM-4PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
- Please be advised on Thursday, March 3rd, the second foundation concrete placement of approximately 600 CY will occur. Anticipated timeline 4AM-1PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
- Please be advised on Friday, March 4th, the third foundation & second wall concrete placements of approximately 400 CY will occur. Anticipated timeline 5AM-4PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: Delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: Delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #36
954045 SOM ED II Construction Alert #36
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, February 19th:
Building Site:
- Removal of 90 ton cranes and final preparations for the mat foundation placement (Equipment: 90 ton RT Crane, delivery trucks, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of February 21st through February 26th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Foundation Placement #1 (Equipment: Concrete trucks, Concrete pumps, light towers, concrete finishing tools & various hand tools).
- Delivery of 350 ton crane (Equipment: 350 ton crane & support trucks).
- Continue rebar for mat foundation placement #2 (Equipment: 350 ton Crane, delivery trucks, various hand tools).
- Begin excavation of foundation placement #3 (Equipment: Excavator, loader, various hand tools).
- Export soil from foundation placement #3 (Equipment: Loader, haul trucks, traffic control).
- Continue wall fabrication (Equipment: 350 ton Crane, forklift, various hand power tools).
- Demolition of existing tunnel vent (Equipment: Excavator, breaker, skid steer, haul trucks, various hand tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that access to the loading docks of Boyce Hall, Scotty’s, SOM ED, and the associated parking stalls in the area is no longer be available. This area will be permanently closed for construction activities. Please utilize the temporary loading dock at the West Courtyard accessible through Parking Lot 11. Please see SOM EDII Temporary Loading Dock Plan exhibit attached.
- Please be advised that the soil export activities will be continuing throughout next week. Soil haul trucks will be present on site and transiting the adjacent areas intermittently throughout the week to support these activities. Please reference Soil Export Traffic Control Plan exhibit.
- Please be advised on Monday, February 21st, the first foundation concrete placement of approximately 1,200 CY will occur. Anticipated timeline 4AM-12PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
New Generator Yard:
- Begin installing the enclosure structural steel. (Equipment: Delivery trucks, concrete trucks, forklift, various hand and power tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
- Please see attached notification from Facilities for the planned electrical power service interruption scheduled for March 1st.
Headhouse 7:
- Continue utility install inside Headhouse 7 (Equipment: Ladders, power tools, various hand tools).
- Continue framing walls for the new headhouse (Equipment: Delivery truck, various hand power tools).
- Begin exterior lath and plaster. (Equipment: Mixer, ladders, air compressor, staple gun and various hand tools.)
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
- Please be advised on Monday, February 21st, the first foundation concrete placement of approximately 1,200 CY will occur. Anticipated timeline 4AM-12PM. There will be multiple concrete trucks required to support this operation. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: Delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: Delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #35
954045 SOM ED II Construction Alert #35
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, February 12th:
Building Site:
- Continue rebar for mat foundation (Equipment: 90 ton RT Crane, delivery trucks, various hand tools).
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of February 14th through February 19th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue rebar of new tower crane pad (Equipment: Delivery trucks, various hand tools).
- Continue rebar for mat foundation (Equipment: 90 ton RT Crane, delivery trucks, various hand tools).
- Continue excavation of foundation placement #2 (Equipment: Excavator, loader, various hand tools).
- Export soil from foundation placement #2 (Equipment: Loader, haul trucks, traffic control).
- Continue abatement of existing fire water line (Equipment: Excavator, delivery trucks, various hand tools).
- Continue wall fabrication (Equipment: 90 ton RT Crane, forklift, various hand power tools).
- Demolition of existing retaining wall (Equipment: Excavator, breaker, skid steer, haul trucks, various hand tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building site.
- Please be advised that access to the loading docks of Boyce Hall, Scotty’s, SOM ED, and the associated parking stalls in the area is no longer be available. This area will be permanently closed for construction activities. Please utilize the temporary loading dock at the West Courtyard accessible through Parking Lot 11. Please see SOM EDII Temporary Loading Dock Plan exhibit attached.
- Please be advised that the soil export activities will be continuing throughout next week. Soil haul trucks will be present on site and transiting the adjacent areas intermittently throughout the week to support these activities. Please reference Soil Export Traffic Control Plan exhibit.
New Generator Yard:
- Continue setting and placing enclosure posts around yard (Equipment: Delivery trucks, concrete trucks, forklift, various hand and power tools).
- Pedestrian access to the North doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
- Please be advised on Thursday, February 17th a concrete pump & truck will be placed on the service road directly south of the new generator yard and Greenhouse #7. Single lane passing in this area will remain available. Access to the Bachelor Hall loading dock will not be affected. Additionally, pedestrian access to the south entrances of Greenhouses #7-10 will remain available. Please reference attached NGY Placement Map exhibit.
Headhouse 7:
- Continue utility install inside Headhouse 7 (Equipment: Ladders, power tools, various hand tools).
- Continue framing walls for the new headhouse (Equipment: Delivery truck, various hand power tools).
- Begin exterior lath. (Equipment: Ladders, air compressor, staple gun and various hand tools.)
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: Delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: Delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #34
954045 SOM ED II Construction Alert #34
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, February 5th:
Building Site:
- Fire water tie in (Equipment: Mini excavator, skid steer, various hand tools).
- Please see attached notification from Facilities for the planned water shutdown affecting SOM ED, scheduled for February 5th.
- Anticipated disturbances: Medium level construction noise and minimal vibration on Building Site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of February 7th through February 12th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue rebar of new tower crane pad (Equipment: Delivery trucks, various hand tools).
- Place rat slab at mat foundation (Equipment: Concrete pump, concrete trucks, various hand tools).
- Deliver 90 ton RT crane to support rebar installation (Equipment: Delivery trucks, traffic control).
- Begin rebar for mat foundation (Equipment: 90 ton RT Crane, delivery trucks, various hand tools).
- Begin excavation of foundation placement #2 (Equipment: Excavator, loader, various hand tools).
- Begin abatement of existing fire water line (Equipment: Excavator, delivery trucks, various hand tools).
- Continue wall fabrication (Equipment: 90 ton RT Crane, forklift, various hand power tools).
- Demolition of existing retaining wall (Equipment: Excavator, breaker, skid steer, haul trucks, various hand tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building Site.
- Please be advised that access to the loading docks of Boyce Hall, Scotty’s, SOM ED, and the associated parking stalls in the area is no longer be available. This area will be permanently closed for construction activities. Please utilize the temporary loading dock at the West Courtyard accessible through Parking Lot 11. Please see SOM EDII Temporary Loading Dock Plan exhibit attached.
- Please be advised that the fire water re-route will be second shift work (2:30 – 11:00 pm).
New Generator Yard:
- Continue setting enclosure posts around yard (Equipment: Delivery trucks, concrete trucks, forklift, various hand and power tools).
- Pedestrian access to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Headhouse 7:
- Continue utility install inside Headhouse 7 (Equipment: Ladders, power tools, various hand tools).
- Continue framing walls for the new headhouse (Equipment: Delivery truck, various hand power tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Greenhouse 8&9:
- Remove remaining asphalt between greenhouses (Equipment: Skid Steer, Haul truck, various hand tools).
- Grade and compact (Equipment: Mini excavator, skid steer, walk behind compactor, various hand tools).
- Rebar and place new drive lane (Equipment: Concrete pump, concrete trucks, various hand tools).
- Anticipated disturbances: Medium to high level construction noise and vibration contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11:
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: Delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: Delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II - Construction Alert #33
954045 SOM ED II Construction Alert #33
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, January 29th:
Building Site:
- Continue grading building pad (Equipment: Loader, dozer, roller, walk behind compactor).
- Anticipated disturbances: Medium level construction noise and minimal vibration on Building Site.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of January 31st through February 5th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Begin excavation of new tower crane pad (Equipment: Skid steer, excavator, haul trucks, various hand tools).
- Begin layout and excavations of footings (Equipment: Excavator, backhoe, various hand tools).
- Begin rebar for mat foundation (Equipment: 90 ton RT Crane, delivery trucks, forklift, various hand tools).
- Continue to export soil from foundations (Equipment: Excavator, haul trucks).
- Begin excavation of new tower crane pad (Equipment: Skid steer, excavator, haul trucks, various hand tools).
- Continue relocation of fire water line (Equipment: Excavator, delivery trucks, various hand tools).
- Continue wall fabrication (Equipment: 90 ton RT Crane, forklift, various hand power tools).
- Pedestrian access at and around SOM ED and to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise and minimal vibration on building Site.
- Please be advised that the soil export activities will be continuing throughout next week. Soil haul trucks will be present on site and transiting the adjacent areas intermittently throughout the week to support these activities. Please see the attached Soil Export Traffic Control Plan exhibit.
- Please be advised that access to the loading docks of Boyce Hall, Scotty’s, SOM ED, and the associated parking stalls in the area is no longer be available. This area will be permanently closed for construction activities. Please utilize the temporary loading dock at the West Courtyard accessible through Parking Lot 11. Please see SOM EDII Temporary Loading Dock Plan exhibit attached.
- Please be advised that the fire water re-route will be second shift work (2:30 – 11:00 pm).
- Please see attached notification from Facilities for the planned water shutdown affecting SOM ED, scheduled for February 10.
New Generator Yard:
- Continue FRP of fence enclosure around yard (Equipment: Delivery trucks, concrete trucks, forklift, various hand and power tools).
- Pedestrian access to the north doors of Headhouses #7-10 will remain open.
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
SOM ED I Existing Electrical Yard (South):
- No activities scheduled for the SOM ED I Generator Yard.
- Pedestrian access to surrounding buildings will remain open.
- Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
Headhouse 7
- Continue utility install inside Headhouse 7 (Equipment: Ladders, power tools, various hand tools).
- Begin framing walls for the new headhouse (Equipment: Delivery truck, various hand power tools).
- Anticipated disturbances: Medium level construction noise contained to surrounding area.
Greenhouse 8&9
- Continue demolition of existing asphalt to improve headhouse access (Equipment: Trucks, skid steer, jackhammers, various power tools and hand tools).
- Anticipated disturbances: Medium to high level construction noise and vibration contained to surrounding area.
West Courtyard:
- Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.
Parking Lot 11
- Activities and access to loading docks will not be affected.
- Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock.
Construction Trailer Area at Parking Lot 10:
- Continue material deliveries to trailer lot (Equipment: Delivery truck).
- Anticipated disturbances: Low level construction noise at Lot 10.
- Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
Parking Lot 41 Laydown Area:
- Material deliveries (Equipment: Delivery trucks, and various hand tools).
- Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
- Activities and access to loading docks will not be affected.
- Anticipated disturbances: Low level construction noise at Lot 41.
Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.
Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.
The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
954045 SOM ED II Construction Alert #32
954045 SOM ED II Construction Alert #32
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, January 22nd:
Building Site:
- Export of soil (Equipment: excavator, dozer haul trucks).
- Continue backfill and compaction of tower crane pad (Equipment: Excavator, skip loader, roller).
- Please be advised there will be traffic control along East Campus Drive in front of the SOM ED II site to support the soil export operation. Please see the attached Soil Export Traffic Control Plan exhibit.
Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of January 24th through January 29th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.
Building Site:
- Continue installation of shoring shotcrete (Equipment: Delivery trucks, concrete trucks, skid steer, forklift, various hand tools).
- Continue