Breadcrumb

UTLF 

The Undergraduate Teaching and Learning Facility (UTLF) project will construct an approximately 120,000 gross-square-foot building to provide UC Riverside with critically needed classroom, class laboratory, and studio space to allow campus to serve current and future undergraduate students.


Project Scope:

UTLF will provide approximately 100,700 gross square feet (GSF) of new academic space. The space program is focused on undergraduate education and incorporates the following types of spaces, which strategically address some of the campus' most pressing instruction and instructional support space needs:

  • General assignment classrooms
  • Specialized teaching spaces such as labs and studios supporting the arts, engineering, and physical and natural sciences
  • Instructional support spaces

 

UTLF Project Updates

  • 950587_UTLF Construction Alert #25

    Current week

     Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Install Underground MEPs

    Excavator, 

    Skip Loader

    Medium-level 

    Construction noise

    Building Site

    Install Sewer Manhole

    Excavator,

     Skip Loader

    Medium-level 

    Construction noise

    Building Site

    Backfill Footings

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium Vibration

    Building Site

    Saturday Work (Earth Work)

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium Vibration

      

    Week of December 09, 2024

     Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Install Underground MEPs

    Excavator, Skip Loader

    Medium-level

    Construction noise

    Building Site

    Install Sewer Manhole

    Excavator, Skip Loader

    Medium-level

    Construction noise

    Building Site

    Fine Grade SOG #1

    Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium Vibration

    Building Site

    Saturday Work (Earth Work/Rebar)

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium Vibration

     

    Week of December 16, 2024 

    Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Install Underground MEPs

    Excavator, 

    Skip Loader

    Medium-level Construction

    noise

    Building Site

    Rebar SOG #1 and #2

    Crane

    Medium-level

    Construction noise

    Building Site

    Pour SOG #1

    Concrete

    Trucks,

    Concrete Pump

    Medium-level

    Construction noise

    Building Site

    Saturday Work (Rebar)

    Crane

    Medium-level

    Construction noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 12/02/24 and 12/06/24.

     

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu

     

     

  • 950587 UTLF Construction Alert #24

    Current week

     Construction Activities

     

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Install Underground MEPs

    Excavator, 

    Skip Loader

    Medium-level Construction

    noise

    Building Site

    Install Sewer Manhole

    Excavator, 

    Skip Loader

    Medium-level Construction

    noise

    Building Site

    Backfill Footings

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, 

    Medium Vibration

     

    Week of December 02, 2024 

    Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Install Underground MEPs

    Excavator,

     Skip Loader

    Medium-level

    Construction noise

    Building Site

    Backfill Footings

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium

    Vibration

    Building Site

    Install Sewer Manhole

    Excavator, Skip Loader

    Medium-level

    Construction noise

    Building Site

    Saturday Work (Earth Work)

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium

    Vibration

     

    Week of December 09, 2024 

    Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Install Underground MEPs

    Excavator, Skip Loader

    Medium-level Construction

    noise

    Building Site

    Fine Grade SOG #1

    Vibratory Roller, Loader, Skip loaderMedium-level Construction noise, Medium Vibration

    Building Site

    Saturday Work (Earth Work)

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium Vibration

      

    Current and Upcoming

     Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities


    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 11/25/24 and 11/29/24.

     Please contact -Sarah Sabera-Turab with any specific questions or concerns at:  sarah.sabera-turab@ucr.edu

  • 950587_UTLF Construction Alert #23

    Current week

     Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Place Columns and Walls Area #2

    Concrete Trucks

    Medium-level Construction

    noise

    Building Site

    Backfill Footings

    Dirt Trucks,

     Vibratory Roller,

     Loader,

    Skip loader

    Medium-level Construction noise, Medium Vibration

    Building Site

    Saturday Work (Earthwork)

    Dirt Trucks,

    Vibratory Roller, 

    Loader,

    Skip loader

    Medium-level Construction noise, Medium Vibration

     

     

    Week of November 25, 2024 

    Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Install Underground MEPsExcavator, Skip Loader

    Medium-level Construction

    noise

    Building Site

    Saturday Work (Earth Work)

    Dirt Trucks, 

    Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium Vibration

    Week of December 02, 2024 

    Construction Activities

    Location

    Activity

    Heavy

    Equipment Used

    Anticipated Disturbance

    Building Site

    Install Underground MEPs

    Excavator, Skip Loader

    Medium-level

    Construction noise

    Building Site

    Saturday Work (Earth Work)

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium Vibration

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    DescriptionLocationDuration & DateImpacted Buildings/ Facilities

     

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 11/18/24 and 11/22/24.

     

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at:

      sarah.sabera-turab@ucr.edu

     

  • 950587 UTLF Construction Alert #22

    Current week 

    Construction Activities

     

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Form / Walls &Columns

    Crane

    Low-level Construction

    noise

    Building Site

    Set Rebar Walls& Columns

    Crane

    Low-level Construction

    noise

    Building Site

    Place Columns and WallsArea #2

    Concrete Trucks

    Medium-level

    Construction noise

    Building Site

    Saturday Work (Stripping Forms)

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium

    Vibration

     

    Week of November 18, 2024 

    Construction Activities

    Location

    Activity

    Heavy

    Equipment Used

    Anticipated Disturbance

    Building Site

    Backfill Footings

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium

    Vibration

    Building Site

    Saturday Work (Earth Work)

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium

    Vibration

     

    Week of November 25, 2024 

    Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Backfill Footings

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium

    Vibration

    Building Site

    Trench Underground MEPs

    Mini Excavator, Skip Loader

    Medium-level

    Construction noise

    Building Site

    Saturday Work (Earth Work)

    Mini Excavator, Skip Loader

    Medium-level

    Construction noise

      

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

        

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 11/11/24 and 11/15/24.

     Please contact -Sarah Sabera-Turab with any specific questions or concerns at:  sarah.sabera-turab@ucr.edu

     

     

  • 950587 UTLF Construction Alert #21

    Current week 

    Construction Activities

     

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Place Foundation #2 (11/4)

    Concrete Trucks

    Medium-level Construction

    noise

    Building Site

    Place Columns andWalls Area #1

    Concrete Trucks

    Medium-level Construction

    noise

    Building Site

    Form / Walls &Columns

    Crane

    Low-level

    Construction noise

    Building Site

    Set Rebar Walls &Columns

    Crane

    Low-level

    Construction noise

    Building Site

    Saturday Work (SetRebar and Formwork)

    Crane

    Low-level

    Construction noise

     

    Week of November 11, 2024 

    Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Form / Walls &Columns

    Crane

    Low-level

    Construction noise

    Building Site

    Set Rebar Walls &Columns

    Crane

    Low-level Construction

    noise

    Building Site

    Place Columns andWalls Area #2

    Concrete Trucks

    Medium-level Construction

    noise

    Building Site

    Backfill Footings

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise, Medium

    Vibration

    Building Site

    Saturday Work (Earth Work)

    Dirt Trucks,

    Vibratory

    Roller, Loader,

    Skip loader

    Medium-level Construction noise,

    Medium Vibration

     

    Week of November 18, 2024 

    Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Backfill Footings

    Dirt Trucks, Vibratory Roller, Loader,

    Skip loader

    Medium-level Construction noise,

     Medium Vibration

    Building Site

    Trench Underground MEPs

    Mini Excavator, Skip Loader

    Medium-level

    Construction noise

    Building Site

    Saturday Work (Earth Work)Mini Excavator, Skip Loader

    Medium-level Construction

    noise

     

     Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Foundation Placement 2

    On Site

    11/04

    No impact on buildings or facilities. Pour will commence at 2am through the morning hours

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 11/04/24 and 11/08/24.

     

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at:  sarah.sabera-turab@ucr.edu

     

     

     

  • 950587 UCR UTLF Construction Alert #20

    Current week

     Construction Activities

     

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Place Foundation #1 (10/29)

    Concrete Trucks

    Medium-level Construction

    noise

    Building Site

    Form / Walls & ColumnsCrane

    Low-level Construction

    noise

    Building Site

    Set Rebar Walls & Columns

    Crane

    Low-level

    Construction noise

    Building Site

    Saturday Work (Set Rebar and Formwork)

    Crane

    Low-level

    Construction noise

     

     

    Week of November 04, 2024

     Construction Activities

    Location

    Activity

    Heavy Equipment

    Used

    Anticipated Disturbance

    Building Site

    Place Foundation #2 (11/4)

    Concrete Trucks

    Medium-level Construction

    noise

    Building Site

    Place Columns and Walls Area #1

    Concrete Trucks

    Medium-level

    Construction noise

    Building Site

    Form / Walls & Columns

    Crane

    Low-level Construction

    noise

    Building Site

    Set Rebar Walls & ColumnsCrane

    Low-level Construction

    noise

    Building Site

    Saturday Work (Set Rebar and Formwork)

    Crane

    Low-level

    Construction noise

     

     Week of November 11, 2024

     Construction Activities

    Location

    Activity

    Heavy

    Equipment Used

    Anticipated Disturbance

    Building Site

    Backfill Footings

    Excavator, Loader,

    Skiploader

    Medium-level Construction

    noise

    Building Site

    Place Columns and Walls Area #1

    Concrete Trucks

    Medium-level

    Construction noise

    Building Site

    Saturday Work (Set Rebar and Formwork)

    Crane

    Low-level Construction

    noise

      

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Foundation Placement 1

    On Site

    10/29

    No impact on buildings or facilities. Pour will commence at 2am through the morning

    hours

    Foundation Placement 2

    On Site

    11/04

    No impact on buildings or facilities. Pour will commence at 2am through the morning

    hours

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 10/28/24 and 11/01/24.

     Please contact -Sarah Sabera-Turab with any specific questions or concerns at:  sarah.sabera-turab@ucr.edu

     

     

  • 950587 UTLF Construction Alert #19 - weeks 10/21/2024- 11/04/2024

    Current week 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Excavate FoundationsExcavator, Skid Steer

    Medium-level Construction

    noise

    Building Site

    Place Rat Slab #1

    Concrete Trucks

    Medium-level

    Construction noise

    Building Site

    Place Rebar Foundations

    Crane

    Medium-level Construction

    noise

     

     Week of October 28, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Place Rat Slab #2

    Concrete Trucks

    Medium-level

    Construction noise

    Building Site

    Place Foundation #1

    Concrete Trucks

    Medium-level Construction

    noise

    Building Site

    Form / Walls & Columns

    Crane

    Medium-level

    Construction noise

    Building Site

    Set Rebar Walls & Columns

    Crane

    Medium-level Construction

    noise

     

    Week of November 04, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Place Foundation #2

    Concrete Trucks

    Medium-level

    Construction noise

    Building Site

    Place Columns and Walls Area #1

    Concrete Trucks

    Medium-level

    Construction noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 10/21/24 and 10/25/24.

     Please contact -Sarah Sabera-Turab with any specific questions or concerns at:  sarah.sabera-turab@ucr.edu

     

     

  • 950587 UTLF Construction Alert #18

    Current week 

    Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Excavate FoundationsExcavator, Skid Steer

    Medium-level Construction

    noise

    Building Site

    Place Rat Slab #1

    Concrete Trucks

    Medium-level

    Construction noise

     

     

    Week of October 21, 2024

     Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Excavate FoundationsExcavator, Skid Steer

    Medium-level Construction

    noise

    Building Site

    Place Concrete Reinforcing

    Crane

    Medium-level

    Construction noise

    Building Site

    Place Rat Slab #2

    Concrete Trucks

    Medium-level Construction

    noise

    Building Site

    Place Foundation #1

    Concrete Trucks

    Medium-level

    Construction noise

     

    Week of October 28, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Excavate Foundations

    Excavator, Skid Steer

    Medium-level Construction

    noise

    Building Site

    Place Concrete Reinforcing

    Crane

    Medium-level

    Construction noise

    Building Site

    Form / Walls & Columns

    Scissor Lift, Crane

    Medium-level

    Construction noise

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 10/14/24 and 10/18/24.

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at:  sarah.sabera-turab@ucr.edu

     

  • 950587 UCR UTLF Construction Alert #17

    Current week 

    Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Excavate FoundationsExcavator, Skid Steer

    Medium-level Construction

    noise

    Building Site

    Place Concrete Reinforcing

    Crane

    Medium-level

    Construction noise

     

     Week of October 14, 2024

     Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Excavate FoundationsExcavator, Skid Steer

    Medium-level Construction

    noise

    Building Site

    Place Concrete Reinforcing

    Crane

    Medium-level

    Construction noise

    Building Site

    Place Rat Slab

    Concrete Trucks

    Medium-level Construction

    noise

     

    Week of October 21, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Excavate Foundations

    Excavator, Skid Steer

    Medium-level Construction

    noise

    Building Site

    Place Concrete Reinforcing

    Crane

    Medium-level Construction

    noise

    Building Site

    Form / Walls & Columns

    Scissor Lift, Crane

    Medium-level

    Construction noise

     

    Current and Upcoming 

    Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 10/07/24 and 10/11/24.

     Please contact -Sarah Sabera-Turab with any specific questions or concerns at:

      sarah.sabera-turab@ucr.edu

     

  • 950587 UTLF Construction Alert #16

    Current week 

    Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Mass Excavation

    Backhoe, dozer, skid steer, Excavator,

    Scraper

    Medium-level Construction noise

    Building Site

    Grade project site

    Backhoe, Dozer, Skid Steer, Excavator,

    Scraper

    Medium-level Construction noise

    Building Site

    Layout Foundations

    Hand Tools

    Low-level construction noise

     

     Week of October 07, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Excavate FoundationsExcavator, Skid Steer

    Medium-level Construction

    noise

    Building Site

    Place Concrete Reinforcing

    Crane

    Medium-level

    Construction noise

     

    Week of October 14, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Excavate Foundations

    Excavator, Skid Steer

    Medium-level

    Construction noise

    Building Site

    Place Concrete Reinforcing

    Crane

    Medium-level Construction

    noise

    Building Site

    Place Rat Slab

    Concrete Trucks

    Medium-level Construction

    noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/30/24 and 10/04/24.

     Please contact -Sarah Sabera-Turab with any specific questions or concerns at:

      sarah.sabera-turab@ucr.edu

     

  • 950587 UTLF Construction Alert #15

    Current week Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Install Water Hydrant (East)

    Backhoe, Hand

    tools,

    Medium-level

    construction noise

    Building Site

    Waterline Tie-In (East)

    Hand Tools

    Low-level construction noise

    Building Site

    Hyrdo-Test Water line (East)

    Hand Tools

    Low-level construction noise

    Building Site

    Mass Excavation

    Backhoe, dozer, skid steer, Excavator,

    Scraper

    Medium-level Construction noise

     

    Week of September 30, 2024 Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Mass Excavation

    Backhoe, dozer, skid steer, Excavator,

    Scraper

    Medium-level Construction noise

    Building Site

    Grade project site

    Backhoe, Dozer, Skid Steer, Excavator,

    Scraper

    Medium-level Construction noise

    Building Site

    Layout Foundations

    Hand Tools

    Low-level

    construction noise

     

    Week of October 7, 2024 

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Building SiteExcavate FoundationsExcavator, Skid Steer

    Medium-level Construction

    noise

    Building SitePlace Concrete ReinforcingCrane

    Medium-level

    Construction noise

     

      Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Water Line Trenching (East)

    Building Site

    8/26/24 (25 days)

    Pedestrian and Vehicle pathways may be

    altered. Safety flagmen will be present. (See TCP Attached)

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/23/24 and 09/27/24.

     

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu

     

  • 950587 UTLF Construction Alert #14

     

    Current Week

    Construction Activities 

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Trench Waterline (East)

    Backhoe, Hand

    tools,

    Medium-level

    construction noise

    Building Site

    Waterline Tie-In (East)

    Hand tools

    Low-level construction noise

    Building Site

    Investigate/Relocate Electrical Line

    Backhoe, Hand toolsMedium-level construction noise

    Building Site

    Excavate and Export Dirt to ND2 Site

    Backhoe, dozer,

    skid steer, Super 10 trucks

    Medium-level

    Construction noise

     

    Week of September 23, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Waterline Tie-In (East)

    Hand tools

    Low-level

    construction noise

    Building Site

    Excavate and Export Dirt to ND2 Site

    Backhoe, dozer,

    skid steer, Super 10 trucks

    Medium-level

    Construction noise

    Building Site

    Chlorinate Water Line (East)

    Backhoe, Hand

    tools

    Medium-level

    construction noise

     

    Week of September 30, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Grade project site

    Backhoe, dozer,

    skid steer, compactor

    Medium-level

    Construction noise

    Building Site

    Place Foundation Rebar

    Crane, Hand tools

    Medium-level Construction

    noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Water Line Trenching (East)

    Building Site

    8/26/24 (20 days)

    Pedestrian and Vehicle pathways may be

    altered. Safety flagmen will be present. (See TCP Attached)

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/16/24 and 09/20/24.

     Please contact -Sarah Sabera-Turab with any specific questions or concerns at  sarah.sabera-turab@ucr.edu

     

     

  • 950587 UCR UTLF Construction Alert #13

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Pothole and Trench Waterline (East)

    Backhoe, Hand

    tools,

    Medium-level

    construction noise

    Building Site

    Investigate/Relocate Electrical Line

    Backhoe, Hand toolsMedium-level construction noise
    ND2 South Parking Area

    Grade Parking Lot

    Backhoe, dozer, skid steer,

    compactor

    Medium-level Construction

    noise

    Building Site

    Grade project site

    Backhoe, dozer,

    skid steer, compactor

    Medium-level

    Construction noise

     

     

    Week of September 9, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines (East)

    Backhoe, Hand

    tools

    Medium-level

    construction noise

    Building Site

    Grade project site

    Backhoe, dozer,

    skid steer, compactor

    Medium-level

    Construction noise

    Building Site

    Chlorinate Water Line (East)

    Backhoe, Hand

    tools

    Medium-level

    construction noise

     

    Week of September 16, 2024

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated

    Disturbance

    Building Site

    Grade project site

    Backhoe, dozer, skid steer,

    compactor

    Medium-level Construction

    noise

         

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Water Line Trenching (East)

    Building Site

    8/26/24 (10 days)

    Pedestrian and Vehicle pathways may be

    altered. Safety flagmen will be present. (See TCP Attached)

    Grade Parking Lot (ND2)

    ND2

    9/09/24 (1 day)

    No impact to building (See revised parking plan)

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/09/24 and 09/13/24.

     

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at  sarah.sabera-turab@ucr.edu

  • 950587 UTLF Construction Alert #11

    Current week

     Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Pothole and Trench Waterline (East)

    Backhoe, Hand

    tools,

    Medium-level

    construction noise

    Building Site

    Investigate/Relocate Electrical Line

    Backhoe, Hand toolsMedium-level construction noise

    Building Site

    Chlorinate Water Line (North)

    Hand Tools

    Low-level construction noise
    ND2 South Parking Area

    Grade Parking Lot

    Backhoe, dozer,

    skid steer, compactor

    Medium-level

    Construction noise

    Building Site

    Grade project site

    Backhoe, dozer, skid steer,

    compactor

    Medium-level Construction

    noise

     

     

    Week of September 2, 2024 Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines (East)

    Backhoe, Hand

    tools

    Medium-level

    construction noise

    Building Site

    Grade project site

    Backhoe, dozer, skid steer,

    compactor

    Medium-level Construction

    noise

     

    Week of September 9, 2024 Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated

    Disturbance

    Building Site

    Chlorinate Water Line (East)Backhoe, Hand tools

    Medium-level construction

    noise

    Building Site

    Grade project site

    Backhoe, dozer,

    skid steer, compactor

    Medium-level

    Construction noise

         

     

     

      

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Water Line Tie- in (North)

    Building Site

    8/26/24 (1 day)

    No impact to building (See USR #1 Attached)

    Water Line Trenching (East)

    Building Site

    8/26/24 (10 days)

    Pedestrian and Vehicle pathways may be altered. Safety flagmen will be present. (See

    TCP Attached)

    Grade Parking Lot (ND2)

    ND2

    8/28/24 (1 day)

    No impact to building (See revised parking plan)

  • 950587 UCR UTLF - Construction Alert #12

    Current week 

    Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Pothole and Trench Waterline (East)

    Backhoe, Hand

    tools,

    Medium-level

    construction noise

    Building Site

    Investigate/Relocate Electrical Line

    Backhoe, Hand toolsMedium-level construction noise

    Building Site

    Chlorinate Water Line (North)

    Hand Tools

    Low-level construction noise

     

     

    Week of September 9, 2024 Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines (East)

    Backhoe, Hand

    tools

    Medium-level

    construction noise

    Building Site

    Grade project site

    Backhoe, dozer,

    skid steer, compactor

    Medium-level

    Construction noise

    ND2 South Parking Area

    Grade Parking Lot

    Backhoe, dozer,

    skid steer, compactor

    Medium-level

    Construction noise

     

    Week of September 16, 2024 Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated

    Disturbance

    Building Site

    Chlorinate Water Line (East)

    Backhoe, Hand tools

    Medium-level construction

    noise

    Building Site

    Grade project site

    Backhoe, dozer, 

    skid steer,

    compactor

    Medium-level Construction

    noise

         

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Water Line Tie- in (North)

    Building Site

    9/03/24 (1 day)

    No impact to building (See USR #1 Attached)

    Water Line Trenching (East)

    Building Site

    8/26/24 (10 days)

    Pedestrian and Vehicle pathways may be altered. Safety flagmen will be present. (See TCP Attached)

    Grade Parking

    Lot (ND2)

    ND2

    9/09/24 (1 day)

    No impact to building (See revised parking

    plan)

     

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/03/24 and 09/06/24.

     

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at  sarah.sabera-turab@ucr.edu

  • 950587 UTLF Construction Alert #10

    Current Week

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines

    Backhoe, Hand

    tools

    Medium-level

    construction noise

    Building Site

    Investigate/Relocate Electrical Line

    Backhoe, Hand tools

    Medium-level construction noise

     

     

    Week of August 26, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines

    Backhoe, Hand

    tools

    Medium-level

    construction noise

    Building Site

    Investigate/Relocate Electrical Line

    Backhoe, Hand

    tools

    Medium-level

    construction noise

    Building Site

    Water Line Tie-In

    Hand Tools

    Low-level

    construction noise

    ND2 South Parking Area

    Grade Parking Lot

    Backhoe, dozer, skid steer,

    compactor

    Medium-level Construction

    noise

    Building Site

    Grade project site

    Backhoe, dozer,

    skid steer, compactor

    Medium-level

    Construction noise

     

    Week of August 02, 2024 

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines (East)

    Backhoe, Hand tools

    Medium-level construction

    noise

    Building Site

    Grade project site

    Backhoe, dozer, skid steer,

    compactor

    Medium-level Construction

    noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Water Line Tie- in

    Building Site

    8/28/24 (1 day)

    No impact to building (See USR #1 Attached)

     

     

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in   street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 08/19/24 and 08/23/24.

     

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at  sarah.sabera-turab@ucr.edu

  • 950587 UTLF Construction Alert #9

    Current week 

    Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Backfill Potholing Utilities

    Backhoe, Hand

    tools

    Low-level

    construction noise

    Building Site

    Relocate Water Lines

    Backhoe, Hand toolsMedium-level construction noise

     

     

    Week of August 19, 2024 Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines

    Backhoe, Hand

    tools

    Medium-level

    construction noise

    Building Site

    Investigate/Relocate Electrical Line

    Backhoe, Hand

    tools

    Medium-level

    construction noise

     

    Week of August 26, 2024 Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines

    Backhoe, Hand tools

    Medium-level construction

    noise

    Building Site

    Water Line Tie-In

    Hand Tools

    Low-level

    construction noise

         

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Water Line Tie- in

    Building Site

    8/28/24 (1 day)

    No impact to building (See USR #1 Attached)

     

  • 950587 UTLF Construction Alert #8

    Current week

     Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Potholing Utilities

    Vac Truck and

    Backhoe

    Medium-level

    construction noise

    Building Site

    Relocate Water Lines

    Backhoe, Hand toolsMedium-level construction noise

    Building Site

    Cut and Cap West Irrigation for Grading of Temp Use AreaSkid Streer, Hand ToolsLow-level construction noise

     

     

    Week of August 12, 2024

     Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Relocate Water Lines

    Backhoe, Hand

    tools

    Medium-level

    construction noise

     

     Week of August 12, 2024

     Construction Activities

    LocationActivityEquipment Used

    Anticipated

    Disturbance

    Building SiteRelocate Water LinesBackhoe, Hand tools

    Medium-level

    construction noise

    Building SiteRelocate Electrical LineBackhoe, Hand toolsMedium-level construction noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

  • 950587 UTLF Construction Alert #7

    Current week

     Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Potholing Utilities

    Vac Truck and

    Backhoe

    Medium-level

    construction noise

    Building Site

    Relocate Water Lines

    Backhoe, Hand tools

    Medium-level construction noise

     

     

    Week of August 05, 2024

     Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

     

    Relocate Water Lines

    Backhoe, Hand

    tools

    Medium-level

    construction noise

     

     

    Week of August 12, 2024

     Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines

    Backhoe, Hand tools

    Medium-level

    construction noise

    Building Site

    Relocate Electrical Line

    Backhoe, Hand tools

    Medium-level construction noise

         

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

  • 950587 UTLF Construction Alert #6

    Current week Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access RoadSlurry Coat

    Slurry Trucks,

    hand tools

    Low-level construction

    noise

    Building Site

    Potholing Utilities

    Vac Truck and Backhoe

    Medium- level construction

    noise

     

     

    Week of July 29, 2024

     Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Potholing Utilities

    Vac Truck and Backhoe

    Medium- level construction

    noise

    Building Site

    Relocate Water Lines

    Backhoe, Hand tools

    Medium- level construction

    noise

     

    Week of August 05, 2024

     Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water LinesBackhoe, Hand tools

    Medium- level construction

    noise

     

     

     Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

  • 950587 UTLF Construction Alert #5

    Current week

     Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access RoadSlurry Coat, Set BarriersForklift, hand tools

    Low-level construction

    noise

    Building Site

    Move North Fence

    Post driver, and hand tools

    Medium- level construction noise, Minor pedestrian traffic

    control

    Building Site

    Potholing Utilities

    Vac Truck and Backhoe

    Medium- level construction

    noise

     

     

    Week of July 22, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Potholing Utilities

    Vac Truck and Backhoe

    Medium- level construction

    noise

    Building Site

    Relocate Water Lines

    Backhoe, Hand tools

    Medium- level construction

    noise

     

    Week of July 29, 2024

     Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines

    Backhoe, Hand tools

    Medium- level construction

    noise

     

     

     Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be

     released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A
  • 950587 UTLF Construction Alert #4

    Current week 

    Construction Activities 

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access RoadBase, Pave, Slurry CoatSkid steer, compactor

    Medium- level construction

    noise

    Building Site

    Clear and Grub, Demo

    Medium excavator, loader, skid steer, dump

    truck

    High-level construction noise

     

     

    Week of July 15, 2024

     Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access Road

    Set Barriers/Fences

    Various hand tools

    Low-level construction

    noise

    Building Site

    Clear and Grub, Demo

    Medium excavator, loader, skid steer, dump

    truck

    High-level construction noise

     

     

    Week of July 22, 2024 

    Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Potholing to located existing utilities

    Vacuum truck, backhoe

    Medium level construction

    noise

     

     

     

    Current and Upcoming Anticipated Closures

     

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

     

  • 950587 UTLF Construction Alert #3

    Current Week Construction Activities.

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp

    Access Road

    Make Ready/ Relocate Utilities

    Various

    Hand Tools

    N/A

    Temp Access Road

    Minor Demo/ Clear and Grub/Build Ramp

    Medium excavator, loader, skid steer, dump

    truck

    Medium- level construction noise

     

     

    Week of July 8, 2024 Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access Road

    Base, Pave, Slurry Coat

    Skid steer, compactor

    Medium- level construction

    noise

    Building Site

    Site Make Ready/ Potholing

    Various Hand Tools, Rotohammer,

    vacuum truck

    Medium- level construction

    noise

    Building Site

    Clear and Grub, Demo

    Medium excavator, loader, skid steer, dump

    truck

    High-level construction noise

     

     

    Week of July 15, 2024 Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access Road

    Set Barriers/Fences

    Various hand tools

    Low-level construction

    noise

    Building Site

    Clear and Grub, Demo

    Medium excavator, loader, skid steer, dump

    truck

    High-level construction noise

     

    Current and Upcoming Anticipated Closures 

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. 

     

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at sarah.sabera-turab@ucr.edu

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

  • 950587 UTLF Construction Alert #2

    UTLF Neighborhood Representatives, 

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the Undergraduate Teaching and Learning Facility (UTLF) during the week of June 24th through June 28th.   

    Building Site

    1. Continue to install Fence and Wind Screen.(Equipment: Post Installer and Various Hand Tools)
    2. Install Job Camera (Equipment: Zoom Boom and Various Hand Tools)
    3. Install Asphalt Ramp at Athletics Building (Equipment: Vibe Plate and Various Hand Tools)

          Anticipated disturbances: Low-level construction noise on Building Site.

     Temp Road

    • Prepping Area for Temp Ramp Install (Equipment: Skip loader)
    • Anticipated disturbances: Medium-level construction noise on Building Site.

    These weekly construction alerts will be posted on a weekly basis on the PDC project website.

    The Undergraduate Teaching and Learning Facility Construction Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you in advance for your patience during construction of this project. 

    Please let us know if you would like to be removed from the project notification email. Also, please advise if you would like us to include additional recipients by responding to this email with the required information.  

  • 950587 UTLF Construction Alert #1

    UTLF Neighborhood Representatives,

    The Undergraduate Teaching and Learning Facility (UTLF) project is in the vicinity of your respective buildings at Parking Lot 19. I’m emailing you on behalf of the project team to inform you about the approaching construction start date for the UTLF building construction and wanted to reach out and provide an update.

    We have been working with McCarthy Building Company to define a logistics and fence plan- which is linked below, and identifies the extents of the construction fenced areas.   
    01 5000 Site Logistics Plan_UCR.pdf 

    Construction Site Fences will start being installed on the 10th of June, followed by construction activities beginning at the end of June.  
     

    The project team and myself plan to have a cadence of weekly or biweekly neighborhood meetings to present a look ahead for construction activities in the upcoming weeks, followed along with a weekly construction alerts notification email.  We will be setting up these neighborhood meeting starting next week- Additional details to follow. 
     

    These weekly construction alerts will be posted on a weekly basis on the PDC project website. Live Feed Cameras will also be available starting in Mid-Late June.  Please let me know if there are any individuals from your team/ department that would need/want to be part of the construction neighborhood meetings (weekly/biweekly) and the weekly construction email alert notifications.
     

    The Undergraduate Teaching and Learning Facility Construction Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. With this effort we aim to be proactive about communicating upcoming work, and be mindful to minimize impact on your operations. We thank you in advance for your patience during construction of this project. 
     

    Please let us know if you would like to be removed from the project notification email. Also, please advise if you would like us to include additional recipients by responding to this email with the required information.  
     

    Thank you
     

    Sarah Sabera-Turab

    PROJECT MANAGER
    Planning, Design & Construction|University of California, Riverside
    1223 UNIVERSITY AVE SUITE 240 | RIVERSIDE CA 92507
    P: 951.827.5825 | C: 951. 584 .6611 | sarah.sabera-turab@ucr.edu

Project Timeline: 

Anticipated Start:
July 2024


Anticipated Completion:
Fall 2026


PD&C Contact:

Project Manager: Sarah Sabera-Turab
tel: (951) 827-5825

Project Planner: Melissa Garrety
tel: (951) 827-7376

Project Working Group:

Ken Baerenklau, Associate Provost, Chair

Bracken Daley, Registrar

Connie Nugent, CNAS Divisional Dean of Student Academic Affairs

Covadonga Lamar Prieto, CHASS Associate Dean of Student Affairs

Huinan Liu, BCOE Associate Dean for Student Academic Affairs

Linda Walling, Chair of the Physical Resources Committee

Architect:

Steinberg Hart

GC:

McCarthy Building Co

 

 

Live Camera