UTLF
The Undergraduate Teaching and Learning Facility (UTLF) project will construct an approximately 120,000 gross-square-foot building to provide UC Riverside with critically needed classroom, class laboratory, and studio space to allow campus to serve current and future undergraduate students.
Project Scope:
UTLF will provide approximately 100,700 gross square feet (GSF) of new academic space. The space program is focused on undergraduate education and incorporates the following types of spaces, which strategically address some of the campus' most pressing instruction and instructional support space needs:
- General assignment classrooms
- Specialized teaching spaces such as labs and studios supporting the arts, engineering, and physical and natural sciences
- Instructional support spaces
UTLF Project Updates
-
950587_UTLF Construction Alert #25
Current week
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Install Underground MEPs
Excavator,
Skip Loader
Medium-level
Construction noise
Building Site
Install Sewer Manhole Excavator,
Skip Loader
Medium-level
Construction noise
Building Site
Backfill Footings
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium Vibration Building Site
Saturday Work (Earth Work)
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium Vibration Week of December 09, 2024
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Install Underground MEPs
Excavator, Skip Loader Medium-level
Construction noise
Building Site
Install Sewer Manhole
Excavator, Skip Loader Medium-level
Construction noise
Building Site
Fine Grade SOG #1
Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium Vibration Building Site
Saturday Work (Earth Work/Rebar)
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium Vibration Week of December 16, 2024
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Install Underground MEPs Excavator,
Skip Loader
Medium-level Construction
noise
Building Site
Rebar SOG #1 and #2
Crane
Medium-level
Construction noise
Building Site
Pour SOG #1
Concrete
Trucks,
Concrete Pump
Medium-level
Construction noise
Building Site
Saturday Work (Rebar)
Crane
Medium-level
Construction noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 12/02/24 and 12/06/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu
-
950587 UTLF Construction Alert #24
Current week
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Install Underground MEPs
Excavator,
Skip Loader
Medium-level Construction
noise
Building Site
Install Sewer Manhole Excavator,
Skip Loader
Medium-level Construction
noise
Building Site
Backfill Footings
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise,
Medium Vibration
Week of December 02, 2024
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Install Underground MEPs
Excavator,
Skip Loader
Medium-level
Construction noise
Building Site
Backfill Footings
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium
Vibration
Building Site
Install Sewer Manhole
Excavator, Skip Loader Medium-level
Construction noise
Building Site
Saturday Work (Earth Work)
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium
Vibration
Week of December 09, 2024
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Install Underground MEPs
Excavator, Skip Loader Medium-level Construction
noise
Building Site
Fine Grade SOG #1
Vibratory Roller, Loader, Skip loader Medium-level Construction noise, Medium Vibration Building Site
Saturday Work (Earth Work)
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium Vibration Current and Upcoming
Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 11/25/24 and 11/29/24.Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu
-
950587_UTLF Construction Alert #23
Current week
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Place Columns and Walls Area #2
Concrete Trucks Medium-level Construction
noise
Building Site
Backfill Footings Dirt Trucks,
Vibratory Roller,
Loader,
Skip loader
Medium-level Construction noise, Medium Vibration Building Site
Saturday Work (Earthwork)
Dirt Trucks,
Vibratory Roller,
Loader,
Skip loader
Medium-level Construction noise, Medium Vibration Week of November 25, 2024
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Install Underground MEPs Excavator, Skip Loader Medium-level Construction
noise
Building Site
Saturday Work (Earth Work)
Dirt Trucks,
Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium Vibration Week of December 02, 2024
Construction Activities
Location
Activity
Heavy
Equipment Used
Anticipated Disturbance
Building Site
Install Underground MEPs
Excavator, Skip Loader Medium-level
Construction noise
Building Site
Saturday Work (Earth Work)
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium Vibration Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description Location Duration & Date Impacted Buildings/ Facilities **No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 11/18/24 and 11/22/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at:
-
950587 UTLF Construction Alert #22
Current week
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Form / Walls &Columns
Crane
Low-level Construction
noise
Building Site
Set Rebar Walls& Columns
Crane
Low-level Construction
noise
Building Site
Place Columns and WallsArea #2
Concrete Trucks
Medium-level
Construction noise
Building Site
Saturday Work (Stripping Forms)
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium
Vibration
Week of November 18, 2024
Construction Activities
Location
Activity
Heavy
Equipment Used
Anticipated Disturbance
Building Site
Backfill Footings
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium
Vibration
Building Site
Saturday Work (Earth Work)
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium
Vibration
Week of November 25, 2024
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Backfill Footings
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium
Vibration
Building Site
Trench Underground MEPs
Mini Excavator, Skip Loader
Medium-level
Construction noise
Building Site
Saturday Work (Earth Work)
Mini Excavator, Skip Loader
Medium-level
Construction noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 11/11/24 and 11/15/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu
-
950587 UTLF Construction Alert #21
Current week
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Place Foundation #2 (11/4)
Concrete Trucks
Medium-level Construction
noise
Building Site
Place Columns andWalls Area #1
Concrete Trucks
Medium-level Construction
noise
Building Site
Form / Walls &Columns
Crane
Low-level
Construction noise
Building Site
Set Rebar Walls &Columns
Crane
Low-level
Construction noise
Building Site
Saturday Work (SetRebar and Formwork)
Crane
Low-level
Construction noise
Week of November 11, 2024
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Form / Walls &Columns
Crane
Low-level
Construction noise
Building Site
Set Rebar Walls &Columns
Crane
Low-level Construction
noise
Building Site
Place Columns andWalls Area #2
Concrete Trucks
Medium-level Construction
noise
Building Site
Backfill Footings
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise, Medium
Vibration
Building Site
Saturday Work (Earth Work)
Dirt Trucks,
Vibratory
Roller, Loader,
Skip loader
Medium-level Construction noise,
Medium Vibration
Week of November 18, 2024
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Backfill Footings
Dirt Trucks, Vibratory Roller, Loader,
Skip loader
Medium-level Construction noise,
Medium Vibration
Building Site
Trench Underground MEPs
Mini Excavator, Skip Loader Medium-level
Construction noise
Building Site
Saturday Work (Earth Work) Mini Excavator, Skip Loader Medium-level Construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description Location
Duration & Date
Impacted Buildings/ Facilities Foundation Placement 2
On Site
11/04
No impact on buildings or facilities. Pour will commence at 2am through the morning hours
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 11/04/24 and 11/08/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu
-
950587 UCR UTLF Construction Alert #20
Current week
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Place Foundation #1 (10/29)
Concrete Trucks Medium-level Construction
noise
Building Site
Form / Walls & Columns Crane Low-level Construction
noise
Building Site
Set Rebar Walls & Columns
Crane
Low-level
Construction noise
Building Site
Saturday Work (Set Rebar and Formwork) Crane
Low-level
Construction noise
Week of November 04, 2024
Construction Activities
Location
Activity
Heavy Equipment
Used
Anticipated Disturbance
Building Site
Place Foundation #2 (11/4)
Concrete Trucks Medium-level Construction
noise
Building Site
Place Columns and Walls Area #1
Concrete Trucks Medium-level
Construction noise
Building Site
Form / Walls & Columns
Crane
Low-level Construction
noise
Building Site
Set Rebar Walls & Columns Crane Low-level Construction
noise
Building Site
Saturday Work (Set Rebar and Formwork) Crane
Low-level
Construction noise
Week of November 11, 2024
Construction Activities
Location
Activity
Heavy
Equipment Used
Anticipated Disturbance
Building Site
Backfill Footings Excavator, Loader,
Skiploader
Medium-level Construction
noise
Building Site
Place Columns and Walls Area #1
Concrete Trucks Medium-level
Construction noise
Building Site
Saturday Work (Set Rebar and Formwork) Crane
Low-level Construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description Location
Duration & Date
Impacted Buildings/ Facilities Foundation Placement 1
On Site
10/29
No impact on buildings or facilities. Pour will commence at 2am through the morning
hours
Foundation Placement 2
On Site
11/04
No impact on buildings or facilities. Pour will commence at 2am through the morning
hours
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 10/28/24 and 11/01/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu
-
950587 UTLF Construction Alert #19 - weeks 10/21/2024- 11/04/2024
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Excavate Foundations Excavator, Skid Steer Medium-level Construction
noise
Building Site
Place Rat Slab #1
Concrete Trucks Medium-level
Construction noise
Building Site
Place Rebar Foundations
Crane
Medium-level Construction
noise
Week of October 28, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Place Rat Slab #2
Concrete Trucks Medium-level
Construction noise
Building Site
Place Foundation #1
Concrete Trucks Medium-level Construction
noise
Building Site
Form / Walls & Columns
Crane
Medium-level
Construction noise
Building Site
Set Rebar Walls & Columns
Crane
Medium-level Construction
noise
Week of November 04, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Place Foundation #2
Concrete Trucks Medium-level
Construction noise
Building Site
Place Columns and Walls Area #1
Concrete Trucks Medium-level
Construction noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
N/A
N/A
N/A
N/A
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 10/21/24 and 10/25/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu
-
950587 UTLF Construction Alert #18
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Excavate Foundations Excavator, Skid Steer Medium-level Construction
noise
Building Site
Place Rat Slab #1
Concrete Trucks Medium-level
Construction noise
Week of October 21, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Excavate Foundations Excavator, Skid Steer Medium-level Construction
noise
Building Site
Place Concrete Reinforcing
Crane
Medium-level
Construction noise
Building Site
Place Rat Slab #2
Concrete Trucks Medium-level Construction
noise
Building Site
Place Foundation #1
Concrete Trucks Medium-level
Construction noise
Week of October 28, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Excavate Foundations
Excavator, Skid Steer Medium-level Construction
noise
Building Site
Place Concrete Reinforcing
Crane
Medium-level
Construction noise
Building Site
Form / Walls & Columns
Scissor Lift, Crane Medium-level
Construction noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
N/A
N/A
N/A
N/A
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 10/14/24 and 10/18/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu
-
950587 UCR UTLF Construction Alert #17
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Excavate Foundations Excavator, Skid Steer Medium-level Construction
noise
Building Site
Place Concrete Reinforcing
Crane
Medium-level
Construction noise
Week of October 14, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Excavate Foundations Excavator, Skid Steer Medium-level Construction
noise
Building Site
Place Concrete Reinforcing
Crane
Medium-level
Construction noise
Building Site
Place Rat Slab
Concrete Trucks Medium-level Construction
noise
Week of October 21, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Excavate Foundations
Excavator, Skid Steer Medium-level Construction
noise
Building Site
Place Concrete Reinforcing
Crane
Medium-level Construction
noise
Building Site
Form / Walls & Columns
Scissor Lift, Crane Medium-level
Construction noise
Current and Upcoming
Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
N/A
N/A
N/A
N/A
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 10/07/24 and 10/11/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at:
-
950587 UTLF Construction Alert #16
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Mass Excavation Backhoe, dozer, skid steer, Excavator,
Scraper
Medium-level Construction noise Building Site
Grade project site
Backhoe, Dozer, Skid Steer, Excavator,
Scraper
Medium-level Construction noise Building Site
Layout Foundations
Hand Tools
Low-level construction noise Week of October 07, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Excavate Foundations Excavator, Skid Steer Medium-level Construction
noise
Building Site
Place Concrete Reinforcing
Crane
Medium-level
Construction noise
Week of October 14, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Excavate Foundations
Excavator, Skid Steer Medium-level
Construction noise
Building Site
Place Concrete Reinforcing
Crane
Medium-level Construction
noise
Building Site
Place Rat Slab
Concrete Trucks Medium-level Construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
N/A
N/A
N/A
N/A
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/30/24 and 10/04/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at:
-
950587 UTLF Construction Alert #15
Current week Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Install Water Hydrant (East) Backhoe, Hand
tools,
Medium-level
construction noise
Building Site
Waterline Tie-In (East)
Hand Tools
Low-level construction noise Building Site
Hyrdo-Test Water line (East)
Hand Tools
Low-level construction noise Building Site
Mass Excavation
Backhoe, dozer, skid steer, Excavator,
Scraper
Medium-level Construction noise Week of September 30, 2024 Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Mass Excavation
Backhoe, dozer, skid steer, Excavator,
Scraper
Medium-level Construction noise Building Site
Grade project site
Backhoe, Dozer, Skid Steer, Excavator,
Scraper
Medium-level Construction noise Building Site
Layout Foundations
Hand Tools
Low-level
construction noise
Week of October 7, 2024
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Building Site Excavate Foundations Excavator, Skid Steer Medium-level Construction
noise
Building Site Place Concrete Reinforcing Crane Medium-level
Construction noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Water Line Trenching (East)
Building Site
8/26/24 (25 days)
Pedestrian and Vehicle pathways may be
altered. Safety flagmen will be present. (See TCP Attached)
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/23/24 and 09/27/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at: sarah.sabera-turab@ucr.edu
-
950587 UTLF Construction Alert #14
Current Week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Trench Waterline (East) Backhoe, Hand
tools,
Medium-level
construction noise
Building Site
Waterline Tie-In (East)
Hand tools
Low-level construction noise Building Site
Investigate/Relocate Electrical Line
Backhoe, Hand tools Medium-level construction noise Building Site
Excavate and Export Dirt to ND2 Site
Backhoe, dozer,
skid steer, Super 10 trucks
Medium-level
Construction noise
Week of September 23, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Waterline Tie-In (East)
Hand tools
Low-level
construction noise
Building Site
Excavate and Export Dirt to ND2 Site
Backhoe, dozer,
skid steer, Super 10 trucks
Medium-level
Construction noise
Building Site
Chlorinate Water Line (East) Backhoe, Hand
tools
Medium-level
construction noise
Week of September 30, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Grade project site
Backhoe, dozer,
skid steer, compactor
Medium-level
Construction noise
Building Site
Place Foundation Rebar
Crane, Hand tools Medium-level Construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Water Line Trenching (East)
Building Site
8/26/24 (20 days)
Pedestrian and Vehicle pathways may be
altered. Safety flagmen will be present. (See TCP Attached)
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/16/24 and 09/20/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at sarah.sabera-turab@ucr.edu
-
950587 UCR UTLF Construction Alert #13
Current Week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Pothole and Trench Waterline (East) Backhoe, Hand
tools,
Medium-level
construction noise
Building Site
Investigate/Relocate Electrical Line
Backhoe, Hand tools Medium-level construction noise ND2 South Parking Area Grade Parking Lot
Backhoe, dozer, skid steer,
compactor
Medium-level Construction
noise
Building Site
Grade project site
Backhoe, dozer,
skid steer, compactor
Medium-level
Construction noise
Week of September 9, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Relocate Water Lines (East)
Backhoe, Hand
tools
Medium-level
construction noise
Building Site
Grade project site
Backhoe, dozer,
skid steer, compactor
Medium-level
Construction noise
Building Site
Chlorinate Water Line (East)
Backhoe, Hand
tools
Medium-level
construction noise
Week of September 16, 2024
Construction Activities
Location
Activity
Equipment Used Anticipated
Disturbance
Building Site
Grade project site Backhoe, dozer, skid steer,
compactor
Medium-level Construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description Location
Duration & Date
Impacted Buildings/ Facilities Water Line Trenching (East)
Building Site
8/26/24 (10 days)
Pedestrian and Vehicle pathways may be
altered. Safety flagmen will be present. (See TCP Attached)
Grade Parking Lot (ND2)
ND2
9/09/24 (1 day)
No impact to building (See revised parking plan)
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/09/24 and 09/13/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at sarah.sabera-turab@ucr.edu
-
950587 UTLF Construction Alert #11
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Pothole and Trench Waterline (East) Backhoe, Hand
tools,
Medium-level
construction noise
Building Site
Investigate/Relocate Electrical Line
Backhoe, Hand tools Medium-level construction noise Building Site
Chlorinate Water Line (North)
Hand Tools
Low-level construction noise ND2 South Parking Area Grade Parking Lot
Backhoe, dozer,
skid steer, compactor
Medium-level
Construction noise
Building Site
Grade project site
Backhoe, dozer, skid steer,
compactor
Medium-level Construction
noise
Week of September 2, 2024 Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Relocate Water Lines (East)
Backhoe, Hand
tools
Medium-level
construction noise
Building Site
Grade project site Backhoe, dozer, skid steer,
compactor
Medium-level Construction
noise
Week of September 9, 2024 Construction Activities
Location
Activity
Equipment Used Anticipated
Disturbance
Building Site
Chlorinate Water Line (East) Backhoe, Hand tools Medium-level construction
noise
Building Site
Grade project site
Backhoe, dozer,
skid steer, compactor
Medium-level
Construction noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description Location
Duration & Date
Impacted Buildings/ Facilities
Water Line Tie- in (North)
Building Site
8/26/24 (1 day)
No impact to building (See USR #1 Attached)
Water Line Trenching (East)
Building Site
8/26/24 (10 days)
Pedestrian and Vehicle pathways may be altered. Safety flagmen will be present. (See
TCP Attached)
Grade Parking Lot (ND2)
ND2
8/28/24 (1 day)
No impact to building (See revised parking plan)
-
950587 UCR UTLF - Construction Alert #12
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Pothole and Trench Waterline (East) Backhoe, Hand
tools,
Medium-level
construction noise
Building Site
Investigate/Relocate Electrical Line
Backhoe, Hand tools Medium-level construction noise Building Site
Chlorinate Water Line (North)
Hand Tools
Low-level construction noise Week of September 9, 2024 Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Relocate Water Lines (East)
Backhoe, Hand
tools
Medium-level
construction noise
Building Site
Grade project site
Backhoe, dozer,
skid steer, compactor
Medium-level
Construction noise
ND2 South Parking Area Grade Parking Lot
Backhoe, dozer,
skid steer, compactor
Medium-level
Construction noise
Week of September 16, 2024 Construction Activities
Location
Activity
Equipment Used
Anticipated
Disturbance
Building Site
Chlorinate Water Line (East)
Backhoe, Hand tools Medium-level construction
noise
Building Site
Grade project site Backhoe, dozer,
skid steer,
compactor
Medium-level Construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description Location
Duration & Date
Impacted Buildings/ Facilities
Water Line Tie- in (North)
Building Site
9/03/24 (1 day)
No impact to building (See USR #1 Attached)
Water Line Trenching (East)
Building Site
8/26/24 (10 days)
Pedestrian and Vehicle pathways may be altered. Safety flagmen will be present. (See TCP Attached)
Grade Parking
Lot (ND2)
ND2
9/09/24 (1 day)
No impact to building (See revised parking
plan)
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 09/03/24 and 09/06/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at sarah.sabera-turab@ucr.edu
-
950587 UTLF Construction Alert #10
Current Week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Relocate Water Lines
Backhoe, Hand
tools
Medium-level
construction noise
Building Site
Investigate/Relocate Electrical Line
Backhoe, Hand tools
Medium-level construction noise
Week of August 26, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Relocate Water Lines
Backhoe, Hand
tools
Medium-level
construction noise
Building Site
Investigate/Relocate Electrical Line
Backhoe, Hand
tools
Medium-level
construction noise
Building Site
Water Line Tie-In
Hand Tools
Low-level
construction noise
ND2 South Parking Area
Grade Parking Lot
Backhoe, dozer, skid steer,
compactor
Medium-level Construction
noise
Building Site
Grade project site
Backhoe, dozer,
skid steer, compactor
Medium-level
Construction noise
Week of August 02, 2024
Construction Activities
Location
Activity
Equipment Used
Anticipated
Disturbance
Building Site
Relocate Water Lines (East)
Backhoe, Hand tools
Medium-level construction
noise
Building Site
Grade project site
Backhoe, dozer, skid steer,
compactor
Medium-level Construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Water Line Tie- in
Building Site
8/28/24 (1 day)
No impact to building (See USR #1 Attached)
**No upcoming or anticipated closures. The constructions operations will occur periodically in street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 08/19/24 and 08/23/24.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at sarah.sabera-turab@ucr.edu
-
950587 UTLF Construction Alert #9
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Backfill Potholing Utilities Backhoe, Hand
tools
Low-level
construction noise
Building Site
Relocate Water Lines
Backhoe, Hand tools Medium-level construction noise Week of August 19, 2024 Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Relocate Water Lines
Backhoe, Hand
tools
Medium-level
construction noise
Building Site
Investigate/Relocate Electrical Line
Backhoe, Hand
tools
Medium-level
construction noise
Week of August 26, 2024 Construction Activities
Location
Activity
Equipment Used Anticipated
Disturbance
Building Site
Relocate Water Lines
Backhoe, Hand tools Medium-level construction
noise
Building Site
Water Line Tie-In
Hand Tools
Low-level
construction noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description Location
Duration & Date
Impacted Buildings/ Facilities
Water Line Tie- in
Building Site
8/28/24 (1 day)
No impact to building (See USR #1 Attached)
-
950587 UTLF Construction Alert #8
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Potholing Utilities Vac Truck and
Backhoe
Medium-level
construction noise
Building Site
Relocate Water Lines
Backhoe, Hand tools Medium-level construction noise Building Site
Cut and Cap West Irrigation for Grading of Temp Use Area Skid Streer, Hand Tools Low-level construction noise Week of August 12, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Relocate Water Lines
Backhoe, Hand
tools
Medium-level
construction noise
Week of August 12, 2024
Construction Activities
Location Activity Equipment Used Anticipated
Disturbance
Building Site Relocate Water Lines Backhoe, Hand tools Medium-level
construction noise
Building Site Relocate Electrical Line Backhoe, Hand tools Medium-level construction noise Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
N/A
N/A
N/A
N/A
-
950587 UTLF Construction Alert #7
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Potholing Utilities
Vac Truck and
Backhoe
Medium-level
construction noise
Building Site
Relocate Water Lines
Backhoe, Hand tools
Medium-level construction noise
Week of August 05, 2024
Construction Activities
Location Activity
Equipment
Used
Anticipated
Disturbance
Relocate Water Lines
Backhoe, Hand
tools
Medium-level
construction noise
Week of August 12, 2024
Construction Activities
Location
Activity
Equipment Used Anticipated
Disturbance
Building Site
Relocate Water Lines
Backhoe, Hand tools
Medium-level
construction noise
Building Site
Relocate Electrical Line
Backhoe, Hand tools
Medium-level construction noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities N/A
N/A
N/A
N/A
-
950587 UTLF Construction Alert #6
Current week Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Temp Access Road Slurry Coat Slurry Trucks,
hand tools
Low-level construction
noise
Building Site
Potholing Utilities
Vac Truck and Backhoe Medium- level construction
noise
Week of July 29, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Potholing Utilities
Vac Truck and Backhoe Medium- level construction
noise
Building Site
Relocate Water Lines
Backhoe, Hand tools Medium- level construction
noise
Week of August 05, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Relocate Water Lines Backhoe, Hand tools Medium- level construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
N/A
N/A
N/A
N/A
-
950587 UTLF Construction Alert #5
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Temp Access Road Slurry Coat, Set Barriers Forklift, hand tools Low-level construction
noise
Building Site
Move North Fence
Post driver, and hand tools Medium- level construction noise, Minor pedestrian traffic
control
Building Site
Potholing Utilities
Vac Truck and Backhoe Medium- level construction
noise
Week of July 22, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Potholing Utilities
Vac Truck and Backhoe Medium- level construction
noise
Building Site
Relocate Water Lines
Backhoe, Hand tools Medium- level construction
noise
Week of July 29, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Relocate Water Lines
Backhoe, Hand tools Medium- level construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be
released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities N/A
N/A
N/A
N/A -
950587 UTLF Construction Alert #4
Current week
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Temp Access Road Base, Pave, Slurry Coat Skid steer, compactor Medium- level construction
noise
Building Site
Clear and Grub, Demo
Medium excavator, loader, skid steer, dump
truck
High-level construction noise Week of July 15, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Temp Access Road Set Barriers/Fences
Various hand tools Low-level construction
noise
Building Site
Clear and Grub, Demo Medium excavator, loader, skid steer, dump
truck
High-level construction noise Week of July 22, 2024
Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Building Site
Potholing to located existing utilities
Vacuum truck, backhoe Medium level construction
noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Description
Location
Duration & Date
Impacted Buildings/ Facilities N/A
N/A
N/A
N/A
-
950587 UTLF Construction Alert #3
Current Week Construction Activities.
Location
Activity
Equipment
Used
Anticipated
Disturbance
Temp
Access Road
Make Ready/ Relocate Utilities
Various
Hand Tools
N/A
Temp Access Road
Minor Demo/ Clear and Grub/Build Ramp
Medium excavator, loader, skid steer, dump
truck
Medium- level construction noise
Week of July 8, 2024 Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Temp Access Road
Base, Pave, Slurry Coat
Skid steer, compactor
Medium- level construction
noise
Building Site
Site Make Ready/ Potholing
Various Hand Tools, Rotohammer,
vacuum truck
Medium- level construction
noise
Building Site
Clear and Grub, Demo
Medium excavator, loader, skid steer, dump
truck
High-level construction noise
Week of July 15, 2024 Construction Activities
Location
Activity
Equipment
Used
Anticipated
Disturbance
Temp Access Road
Set Barriers/Fences
Various hand tools
Low-level construction
noise
Building Site
Clear and Grub, Demo
Medium excavator, loader, skid steer, dump
truck
High-level construction noise
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.
Please contact -Sarah Sabera-Turab with any specific questions or concerns at sarah.sabera-turab@ucr.edu
Description
Location
Duration & Date
Impacted Buildings/ Facilities
N/A
N/A
N/A
N/A
-
950587 UTLF Construction Alert #2
UTLF Neighborhood Representatives,
Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the Undergraduate Teaching and Learning Facility (UTLF) during the week of June 24th through June 28th.
Building Site
- Continue to install Fence and Wind Screen.(Equipment: Post Installer and Various Hand Tools)
- Install Job Camera (Equipment: Zoom Boom and Various Hand Tools)
- Install Asphalt Ramp at Athletics Building (Equipment: Vibe Plate and Various Hand Tools)
Anticipated disturbances: Low-level construction noise on Building Site.
Temp Road
- Prepping Area for Temp Ramp Install (Equipment: Skip loader)
- Anticipated disturbances: Medium-level construction noise on Building Site.
These weekly construction alerts will be posted on a weekly basis on the PDC project website.
The Undergraduate Teaching and Learning Facility Construction Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you in advance for your patience during construction of this project.
Please let us know if you would like to be removed from the project notification email. Also, please advise if you would like us to include additional recipients by responding to this email with the required information.
- Continue to install Fence and Wind Screen.(Equipment: Post Installer and Various Hand Tools)
-
950587 UTLF Construction Alert #1
UTLF Neighborhood Representatives,
The Undergraduate Teaching and Learning Facility (UTLF) project is in the vicinity of your respective buildings at Parking Lot 19. I’m emailing you on behalf of the project team to inform you about the approaching construction start date for the UTLF building construction and wanted to reach out and provide an update.
We have been working with McCarthy Building Company to define a logistics and fence plan- which is linked below, and identifies the extents of the construction fenced areas.
01 5000 Site Logistics Plan_UCR.pdfConstruction Site Fences will start being installed on the 10th of June, followed by construction activities beginning at the end of June.
The project team and myself plan to have a cadence of weekly or biweekly neighborhood meetings to present a look ahead for construction activities in the upcoming weeks, followed along with a weekly construction alerts notification email. We will be setting up these neighborhood meeting starting next week- Additional details to follow.
These weekly construction alerts will be posted on a weekly basis on the PDC project website. Live Feed Cameras will also be available starting in Mid-Late June. Please let me know if there are any individuals from your team/ department that would need/want to be part of the construction neighborhood meetings (weekly/biweekly) and the weekly construction email alert notifications.
The Undergraduate Teaching and Learning Facility Construction Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. With this effort we aim to be proactive about communicating upcoming work, and be mindful to minimize impact on your operations. We thank you in advance for your patience during construction of this project.
Please let us know if you would like to be removed from the project notification email. Also, please advise if you would like us to include additional recipients by responding to this email with the required information.
Thank you
Sarah Sabera-Turab
PROJECT MANAGER
Planning, Design & Construction|University of California, Riverside
1223 UNIVERSITY AVE SUITE 240 | RIVERSIDE CA 92507
P: 951.827.5825 | C: 951. 584 .6611 | sarah.sabera-turab@ucr.edu
Project Timeline:
Anticipated Start:
July 2024
Anticipated Completion:
Fall 2026
PD&C Contact:
Project Manager: Sarah Sabera-Turab
tel: (951) 827-5825
Project Planner: Melissa Garrety
tel: (951) 827-7376
Project Working Group:
Ken Baerenklau, Associate Provost, Chair
Bracken Daley, Registrar
Connie Nugent, CNAS Divisional Dean of Student Academic Affairs
Covadonga Lamar Prieto, CHASS Associate Dean of Student Affairs
Huinan Liu, BCOE Associate Dean for Student Academic Affairs
Linda Walling, Chair of the Physical Resources Committee
Architect:
Steinberg Hart
GC:
McCarthy Building Co