Breadcrumb

UTLF 

The Undergraduate Teaching and Learning Facility (UTLF) project will construct an approximately 120,000 gross-square-foot building to provide UC Riverside with critically needed classroom, class laboratory, and studio space to allow campus to serve current and future undergraduate students.


Project Scope:

UTLF will provide approximately 100,700 gross square feet (GSF) of new academic space. The space program is focused on undergraduate education and incorporates the following types of spaces, which strategically address some of the campus' most pressing instruction and instructional support space needs:

  • General assignment classrooms
  • Specialized teaching spaces such as labs and studios supporting the arts, engineering, and physical and natural sciences
  • Instructional support spaces

 

UTLF Project Updates

  • 950587 UTLF Construction Alert #5

    Current week

     Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access RoadSlurry Coat, Set BarriersForklift, hand tools

    Low-level construction

    noise

    Building Site

    Move North Fence

    Post driver, and hand tools

    Medium- level construction noise, Minor pedestrian traffic

    control

    Building Site

    Potholing Utilities

    Vac Truck and Backhoe

    Medium- level construction

    noise

     

     

    Week of July 22, 2024 

    Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Potholing Utilities

    Vac Truck and Backhoe

    Medium- level construction

    noise

    Building Site

    Relocate Water Lines

    Backhoe, Hand tools

    Medium- level construction

    noise

     

    Week of July 29, 2024

     Construction Activities

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Relocate Water Lines

    Backhoe, Hand tools

    Medium- level construction

    noise

     

     

     Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be

     released weekly in the Project Construction Advisories until the work is complete.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A
  • 950587 UTLF Construction Alert #4

    Current week 

    Construction Activities 

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access RoadBase, Pave, Slurry CoatSkid steer, compactor

    Medium- level construction

    noise

    Building Site

    Clear and Grub, Demo

    Medium excavator, loader, skid steer, dump

    truck

    High-level construction noise

     

     

    Week of July 15, 2024

     Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access Road

    Set Barriers/Fences

    Various hand tools

    Low-level construction

    noise

    Building Site

    Clear and Grub, Demo

    Medium excavator, loader, skid steer, dump

    truck

    High-level construction noise

     

     

    Week of July 22, 2024 

    Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Building Site

    Potholing to located existing utilities

    Vacuum truck, backhoe

    Medium level construction

    noise

     

     

     

    Current and Upcoming Anticipated Closures

     

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

     

  • 950587 UTLF Construction Alert #3

    Current Week Construction Activities.

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp

    Access Road

    Make Ready/ Relocate Utilities

    Various

    Hand Tools

    N/A

    Temp Access Road

    Minor Demo/ Clear and Grub/Build Ramp

    Medium excavator, loader, skid steer, dump

    truck

    Medium- level construction noise

     

     

    Week of July 8, 2024 Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access Road

    Base, Pave, Slurry Coat

    Skid steer, compactor

    Medium- level construction

    noise

    Building Site

    Site Make Ready/ Potholing

    Various Hand Tools, Rotohammer,

    vacuum truck

    Medium- level construction

    noise

    Building Site

    Clear and Grub, Demo

    Medium excavator, loader, skid steer, dump

    truck

    High-level construction noise

     

     

    Week of July 15, 2024 Construction Activities

     

    Location

    Activity

    Equipment

    Used

    Anticipated

    Disturbance

    Temp Access Road

    Set Barriers/Fences

    Various hand tools

    Low-level construction

    noise

    Building Site

    Clear and Grub, Demo

    Medium excavator, loader, skid steer, dump

    truck

    High-level construction noise

     

    Current and Upcoming Anticipated Closures 

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. 

     

    Please contact -Sarah Sabera-Turab with any specific questions or concerns at sarah.sabera-turab@ucr.edu

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    N/A

    N/A

    N/A

    N/A

  • 950587 UTLF Construction Alert #2

    UTLF Neighborhood Representatives, 

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the Undergraduate Teaching and Learning Facility (UTLF) during the week of June 24th through June 28th.   

    Building Site

    1. Continue to install Fence and Wind Screen.(Equipment: Post Installer and Various Hand Tools)
    2. Install Job Camera (Equipment: Zoom Boom and Various Hand Tools)
    3. Install Asphalt Ramp at Athletics Building (Equipment: Vibe Plate and Various Hand Tools)

          Anticipated disturbances: Low-level construction noise on Building Site.

     Temp Road

    • Prepping Area for Temp Ramp Install (Equipment: Skip loader)
    • Anticipated disturbances: Medium-level construction noise on Building Site.

    These weekly construction alerts will be posted on a weekly basis on the PDC project website.

    The Undergraduate Teaching and Learning Facility Construction Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you in advance for your patience during construction of this project. 

    Please let us know if you would like to be removed from the project notification email. Also, please advise if you would like us to include additional recipients by responding to this email with the required information.  

  • 950587 UTLF Construction Alert #1

    UTLF Neighborhood Representatives,

    The Undergraduate Teaching and Learning Facility (UTLF) project is in the vicinity of your respective buildings at Parking Lot 19. I’m emailing you on behalf of the project team to inform you about the approaching construction start date for the UTLF building construction and wanted to reach out and provide an update.

    We have been working with McCarthy Building Company to define a logistics and fence plan- which is linked below, and identifies the extents of the construction fenced areas.   
    01 5000 Site Logistics Plan_UCR.pdf 

    Construction Site Fences will start being installed on the 10th of June, followed by construction activities beginning at the end of June.  
     

    The project team and myself plan to have a cadence of weekly or biweekly neighborhood meetings to present a look ahead for construction activities in the upcoming weeks, followed along with a weekly construction alerts notification email.  We will be setting up these neighborhood meeting starting next week- Additional details to follow. 
     

    These weekly construction alerts will be posted on a weekly basis on the PDC project website. Live Feed Cameras will also be available starting in Mid-Late June.  Please let me know if there are any individuals from your team/ department that would need/want to be part of the construction neighborhood meetings (weekly/biweekly) and the weekly construction email alert notifications.
     

    The Undergraduate Teaching and Learning Facility Construction Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. With this effort we aim to be proactive about communicating upcoming work, and be mindful to minimize impact on your operations. We thank you in advance for your patience during construction of this project. 
     

    Please let us know if you would like to be removed from the project notification email. Also, please advise if you would like us to include additional recipients by responding to this email with the required information.  
     

    Thank you
     

    Sarah Sabera-Turab

    PROJECT MANAGER
    Planning, Design & Construction|University of California, Riverside
    1223 UNIVERSITY AVE SUITE 240 | RIVERSIDE CA 92507
    P: 951.827.5825 | C: 951. 584 .6611 | sarah.sabera-turab@ucr.edu

Project Timeline: 

Anticipated Start:
July 2024


Anticipated Completion:
Fall 2026


PD&C Contact:

Project Manager: Sarah Sabera-Turab
tel: (951) 827-5825

Project Planner: Melissa Garrety
tel: (951) 827-7376

Project Working Group:

Ken Baerenklau, Associate Provost, Chair

Bracken Daley, Registrar

Connie Nugent, CNAS Divisional Dean of Student Academic Affairs

Covadonga Lamar Prieto, CHASS Associate Dean of Student Affairs

Huinan Liu, BCOE Associate Dean for Student Academic Affairs

Linda Walling, Chair of the Physical Resources Committee

Architect:

Steinberg Hart

GC:

McCarthy Building Co