School of Business New Building

The new School of Business building complex will be a flagship facility, serving as the permanent home for the School. The building will complement the School of Business’ existing space program and fully address enrollment-driven needs in pursuit of their aspiration to become the premier center of management research and education in the Inland Empire.


Project Scope:

The proposed building will provide about 38,500 ASF within approximately to 63,400 GSF, along with exterior circulation and gathering areas. The program includes the following spaces:

  • Classrooms and Educational Spaces
  • Student Support Spaces
  • Academic Offices and Support Spaces
  • Administrative Offices and Support Spaces
  • Shared Building Resources (Lobby, Multipurpose room(s) etc)

School of Business Project Updates

  • 950592 UCR SBB - Construction Alert #44

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Install Metal Decking

    Gradall

    Noise due to equipment

    BIO

    Framing and Insulation

    Gradall

    Noise due to equipment

    SBB (Lot 8) Concrete

    Deck Pour – L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEPs – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Pour – L2S

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Deck Depressions – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Install Embeds – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Embeds – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2S

    Crane

    Noise due to Equipment

     

    Week of September 18, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Parapet Coping/Flashing/Louvers

    NA

    NA

    BIO

    Downspouts

    NA

    NA

    BIO

    In-Wall and overhead plumbing work

    NA

    NA

    BIO

    Set fan coil units

    NA

    NA

    SBB (Lot 8) Concrete

    Strip & Re-Shore – Deck L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection– Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms– Vertical L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour– Vertical L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Pour – Deck L2S

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – Deck L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams– Deck L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – Vert L2S

    NA

    NA

    SBB (Lot 8) Concrete

    One side form walls and columns – Vert L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar – Vert L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Vert L2S

    NA

    NA

     

    Week of September 25, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    In-Wall & Overhead Electrical Rough-in

    NA

    NA

    BIO

    Pull Electrical and Low Voltage Wire

    NA

    NA

    BIO

    Fine Grade for Finish Site Work

    Heavy Equipment

    Noise due to Equipment

    BIO

    F/R/P Equipment Pads

    NA

    NA

    BIO

    F/R/P New Flatwork to Tie Into Existing

    NA

    NA

    SBB (Lot 8) Concrete

    Strip Walls and Columns – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds - Vertical L2S

    NA

    NA

    SBB (Lot 8) Concrete

    QC Inspection - Vertical L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Close two side forms - Vertical L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour  - Vertical L2S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip walls & Columns  - Vertical L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Form Deck – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form – Deck L3N

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #43

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Pour SOG

    Concrete Pump

    Noise due to Equipment

    BIO

    Backfill

    Mini-Excavator

    Noise due to Equipment

    BIO

    Erect Steel Roof Structure

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC / Inspection – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Embeds – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2S

    Crane

    Noise due to Equipment

     

    Week of September 11, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Install Metal Decking

    Gradall

    Noise due to equipment

    SBB (Lot 8) Concrete

    Deck Pour – L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEPs – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Pour – L2S

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Deck Depressions – L2S

    NA

    NA

     

    Week of September 18, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Install Door Frames

    NA

    NA

    BIO

    Install Doors and Hardware

    NA

    NA

    BIO

    Install Roofing System

    Gradall

    Noise due to equipment

    BIO

    Install Electrical Panels

    NA

    NA

    SBB (Lot 8) Concrete

    Strip & Re-Shore – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Vertical Pour – L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls and Columns – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar – L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEPs – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Form Deck – L3N

    NA

    NA

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #42

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Fine Grade – SOG

    N/A

    N/A

    BIO

    Concrete

    Vapor Barrier – SOG

    N/A

    N/A

    BIO

    Concrete

    Rebar – SOG

    Gradall

    Noise due to Equipment

    BIO

    Concrete

    QC/ Inspection – SOG

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour SOG 2 – L1S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Chilled Water

    Mini-excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Install Embeds

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves & Inserts

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions

    N/A

    N/A

     

    Week of September 4, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Pour SOG

    Concrete Pump

    Noise due to Equipment

    BIO

    Backfill

    Mini-Excavator

    Noise due to Equipment

    BIO

    Erect Steel Roof Structure

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC / Inspection – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Embeds – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2S

    Crane

    Noise due to Equipment

     

    Week of September 11, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Bio

    Install Metal Decking

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout and Install MEPs – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Depressions – L2S

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #41

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Plumbing Rough-in

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8)

    Sitework

    Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Q/C Inspection – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG South

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG South

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Deck

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    Week of August 28, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Fine Grade – SOG

    N/A

    N/A

    BIO

    Concrete

    Vapor Barrier – SOG

    N/A

    N/A

    BIO

    Concrete

    Rebar – SOG

    Gradall

    Noise due to Equipment

    BIO

    Concrete

    QC/ Inspection – SOG

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour SOG 2 – L1S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Chilled Water

    Mini-excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Install Embeds

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves & Inserts

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions

    N/A

    N/A

     

    Week of September 4, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Pour SOG

    Concrete Pump

    Noise due to Equipment

    BIO

    Erect Steel Roof Structure

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form – L2S

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #40

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    CMU Walls

    Set Scaffold and Erect CMU Block Structure

    Gradall

    Noise due to Equipment

    BIO

    CMU Walls

    Set Anchor Bolts

    N/A

    N/A

    BIO

    CMU Walls

    Grout/Clean-Up/Remove Scaffold

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Install Electrical Rough-in – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In – SOG South

    N/A       

    N/A

    SBB (Lot 8)

    Concrete

    Fine Grade – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Install Vapor Barrier – SOG South

    N/A

    N/A

     

    Week of August 21, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Plumbing Rough-in

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8)

    Sitework

    Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Q/C Inspection – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG South

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG South

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Deck

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    Week of August 28, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Fine Grade – SOG

    N/A

    N/A

    BIO

    Concrete

    Vapor Barrier – SOG

    N/A

    N/A

    BIO

    Concrete

    Rebar – SOG

    Gradall

    Noise due to Equipment

    BIO

    Concrete

    QC/ Inspection – SOG

    N/A

    N/A

    SBB (Lot 8) Sitework

    Chilled Water

    Mini-excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Install Embeds

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves & Inserts

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions

    N/A

    N/A

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #39

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Plumbing Rough-In

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Electrical Rough-In

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    QC / Inspection – SOG North

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In

    N/A       

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls & Columns – SOG South

    Dump Truck

    Noise due to Equipment

     

    Week of August 14, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    CMU Walls

    Set Scaffold & Erect CMU Block Structure

    Forklift

    Noise due to Equipment

    SBB (Lot 8)

    Sitework

    Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Fine Grade – SOG South

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deliver/ Shake Out Elevated Deck Form Work

    Delivery Trucks

    Noise due to Equipment

     

    Week of August 21, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    CMU Walls

    Set Anchor Bolts

    N/A

    N/A

    BIO

    CMU Walls

    Grout / Clean-up / Remove Scaffold CMU Walls

    N/A

    N/A

    SBB (Lot 8) Sitework

    Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG South

    Concrete Pumps and Trucks

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Rebar – SOG South

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG South

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Deck

    Crane

    Noise Due to Equipment

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #38

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Foundations

    Excavate Foundations

    Mini-Excavator and Skid Steer

    Noise due to Equipment

    BIO

    Foundations

    Rebar Foundations

    N/A

    N/A

    BIO

    Foundations

    QC/ Inspection Foundations

    N/A

    N/A

    BIO

    Foundations

    Pour Foundations

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Close Two Side Form – Core Wall – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Core Wall – Pour 2

    Concrete Pumps and Trucks

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Strip Walls – Core Walls – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Removed Rebound – Retaining Wall

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffold

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footings, Walls & Columns – SOG North

    Dump Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Fine Grade – SOG North

    Skid Steer

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In

    N/A

    N/A

     

    Week of August 7, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Plumbing Rough-In

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Electrical Rough-In

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    QC / Inspection – SOG North

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In

    N/A            

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls & Columns – SOG South

    Dump Truck

    Noise due to Equipment

     

    Week of August 14, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    CMU Walls

    Set Scaffold & Erect CMU Block Structure

    N/A

    N/A

    SBB (Lot 8) Concrete

    Fine Grade – SOG South

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deliver/ Shake Out Elevated Deck Form Work

    Delivery Trucks

    Noise due to Equipment

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #37

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Remove (E) Electrical

    Mini-Excavator and Skid Steer

    Noise due to Equipment

    BIO

    Sitework

    Grade Site & Building Pad

    Mini-Excavator and Skid Steer

    Noise due to Equipment

    BIO

    Sitework

    Building Pad Certification

    N/A

    N/A

    SBB (Lot 8) Sitework

    Pothole Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Rebar – Core Walls – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    One Side Form Walls – Core Wall – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Layout & Install MEP’s – Core Walls – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC/ Inspection – Core Walls – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds – Core Wall – Pour 2

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Close Two Side Forms – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 3

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Set Scaffold – Retaining Wall

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Stub-Up

    N/A

    N/A

     

    Week of July 31, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Foundation

    Layout Foundation

    N/A

    N/A

    BIO

    Foundation

    Excavate Foundations

    Excavator

    Noise due to Equipment

    BIO

    Foundation

    Rebar Foundations

    N/A

    N/A

    BIO Foundations

    QC/ Inspection Foundations

    N/A

    N/A

     

    BIO Foundations

    Pour Foundations

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Core Walls – Pour 2

    Concrete Pumps and Trucks

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Strip Walls – Core Walls – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Shotcrete Wires – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete Pump and Trucks

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

     

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Remove Scaffold – Retaining Wall

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls, & Columns – SOG North

    Dump Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Fine Grade – SOG North

    Skid Steer

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-in – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls, & Columns – SOG South

    Dump Trucks

    Noise due to Equipment

     

    Week of August 07, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Utilities Plumbing Rough-In

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Utilities Electrical Rough-In

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar - SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG North

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In – SOG South

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    College Pl

    College Pl

    7/10 – 7/28

    The College Pl loop is a one-way (single lane) road that branches off S Campus Dr. The Southern College Pl Road contains two traffic control operators helping direct traffic both to and from Parking Lot 3. The Northern College Pl Road has been closed.

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #36

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Relocate (E) Steam Line

    Mini-Excavator and Skid Steer

    Noise due to Equipment

     

    BIO

    Sitework

    Test & Backfill Steam Line

    Skid Steer

    Noise due to Equipment

     

    BIO

    Sitework

    Remove (E) Electrical Line

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Strip – Column Pour 1

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Waterblast – Column Pour 1

    Concrete Pressure Washer

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Strip Walls – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Rebar – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Layout & Install MEP’s – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Set Embeds – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    QC / Inspection – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Close Two Side Forms – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffolding – Retaining Wall North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill – Retaining Wall

    Trucks and Excavator

    Noise due to Equipment

    SBB (Lot 8) Sitework

    MEP Layout & Block outs – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Sitework

    Rebar – Retaining Wall

    N/A

    N/A

    SBB (Lot 8)

    Sitework

    Set Scaffolding – Retaining Wall South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls & Columns – SOG North

    Excavator

    Noise due to Equipment

    SBB (Lot 8)

    Bio-Retention Planter

    Backfill Bio-Retention Planter for Steam Lines

    Excavator

     

    Noise due to Equipment

     

    Week of July 24, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Remove (E) Electrical

    Mini-Excavator and Skid Steer

    Noise due to Equipment

    BIO

    Sitework

    Grade Site & Building Pad

    N/A

    N/A

    BIO

    Sitework

    Building Pad Certification

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 3

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Wires

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Shotcrete -Retaining Wall

    Shotcrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffolding – Retaining Wall

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Fine Grade – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-in – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-in – SOG South

    N/A

    N/A

     

    Week of July 31, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Foundations

    Layout Foundations

    N/A

    N/A

    BIO

    Foundations

    Excavate Foundations

    Excavator

    Noise due to Equipment

    BIO

    Foundations

    Rebar Foundations

    N/A

    N/A

    BIO

    Foundations

    QC/Inspection Foundations

    N/A

    N/A

    BIO

    Foundations

    Pour Foundations

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Backfill - Retaining Wall

    Dump Truck(s)

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG North

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Fine Grade – SOG South

    skip loader

    Noise due to Equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    College Pl

    College Pl

    7/10 – 7/28

    The College Pl loop is a one-way (single lane) road that branches off S Campus Dr. The Southern College Pl Road contains two traffic control operators helping direct traffic both to and from Parking Lot 3. The Northern College Pl Road has been closed.

  • 950592 UCR SBB - Construction Alert #35

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Relocate (E) Steam Line

    Mini-Excavator and Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Close Two Side Forms – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 2

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    One Side Form Walls – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8)

    Concrete

    Electrical Rough-in – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC/Inspection – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Columns – Columns – Column Pour 1

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Pour – Column Pour 1

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Set – Scaffolding – Retaining Wall North

    N/A

    N/A

    SBB (Lot 8) Sitework

    Shotcrete Wires – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Sitework

    Back Form – Retaining Wall

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Waterproofing – Retaining Wall – at Mat Pour 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Stub-up – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Bio-Retention Planter

    Excavate Bio-retention planter for steam lines

    Excavator

    Noise due to Equipment

     

    Week of July 17, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Relocate (E) Steam Line

    Mini-Excavator and Skid Steer

    Noise due to Equipment

     

    BIO

    Sitework

    Test & Backfill Steam Line

    Skid Steer

    Noise due to Equipment

     

    BIO

    Sitework

    Remove (E) Electrical Line

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Strip – Column Pour 1

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Waterblast – Column Pour 1

    Concrete Pressure Washer

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Strip Walls – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Rebar – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Layout & Install MEP’s – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Set Embeds – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    QC / Inspection – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Close Two Side Forms – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffolding – Retaining Wall North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill – Retaining Wall

    Trucks and Excavator

    Noise due to Equipment

    SBB (Lot 8) Sitework

    MEP Layout & Block outs – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Sitework

    Rebar – Retaining Wall

    N/A

    N/A

    SBB (Lot 8)

    Sitework

    Set Scaffolding – Retaining Wall South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls & Columns – SOG North

    Excavator

    Noise due to Equipment

    SBB (Lot 8)

    Bio-Retention Planter

    Backfill Bio-Retention Planter for Steam Lines

    Excavator

     

    Noise due to Equipment

     

    Week of July 24, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 3

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Wires

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Shotcrete -Retaining Wall

    Shotcrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffolding – Retaining Wall

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Fine Grade – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-in – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-in – SOG South

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #34

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour Mat Footing 2

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 1

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Strip Walls – Shear Walls & Columns – Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    QC Inspection Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Close Two-Side Forms – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Set Rebar Column Cages – Column Pour 1

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Electrical Rough-In – Column Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Form Columns – Column Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Waterproofing – Retaining Wall – at Mat Pour 2

    Boom Lift

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Back Form – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Layouts & Blockouts – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Bio-Retention Planter

    Excavate Bio-retention planter for steam lines

    Excavator

    Noise due to Equipment

     

    Week of July 10, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Strip – Columns Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterblast – Column Pour 1

    Concrete Pressure Washer

    Noise due to equipment

    SBB (Lot 8) Concrete

    Set Scaffolding – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Shotcrete Wires – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footings, Walls & Columns – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Storm Drain at Auditorium

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Underslab Electrical Stub-up – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footing, Walls, & Columns – SOG South

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Bio-Retention Planter

    Excavate Bio-retention planter for steam lines

    Excavator

    Noise due to Equipment

     

    Week of July 17, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Remove Scaffold – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill – Retaining Wall

     

    Trucks

    Noise due to equipment

    SBB (Lot 8) Bio-Retention Planter

    Excavate Bio-retention planter for steam lines

    Excavator

    Noise due to Equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #33

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Strip and Waterblast Mat Footing 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Wall & Column Templates and Dowels – Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection at Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Spread Continuous Footings

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Wall and Column Templates – Spread Footings

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Waterblast Dowels – Spread Footings

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Rebar Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Electrical Rough-in – Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Set Embeds – Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    QC Inspection Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Close up Wall Forms – Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Layout Walls – Shear Walls and Columns – For Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterproofing – Retaining Wall at Mat Pour 1

    N/A

    N/A

     

    Week of July 3, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Mat Footing 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 1

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection Shear Walls & Columns – Pour 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Close Two-Side Forms – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Rebar Column Cages – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Electrical Rough-in – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Columns – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterproofing – Retaining Wall – at Mat Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Back Form – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Layouts & Blockouts – Retaining Wall

    N/A

    N/A

     

    Week of July 10, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls - Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Strip – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterblast – Column Pour 1

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Scaffolding – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Shotcrete Wires – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footing, Walls & Columns – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Storm Drain at Auditorium

    N/A

    N/A

    SBB (Lot 8) Concrete

    Underslab Electrical Stub-up – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footing, Walls, & Columns – SOG South

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #32

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Qc Inspection Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Mat Footing 1

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip and Waterblast Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Storm Drain at Auditorium

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Wall & Column Templates and Dowels Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Spread Footings

    N/A

    N/A

     

    Week of June 26, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC inspection at Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Mat Footing 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip and Waterblast Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Wall & Column Templates and Dowels - Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC inspection at Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Spread Continuous Footings

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Wall and Column Templates – Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterblast Dowels – Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar Shear Walls and Columns  - For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Electrical Rough-in - Shear Walls and Columns - For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds - Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC inspection Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Close Up Wall Forms – Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout Walls – Shear Walls and Columns – For Pour 2

    N/A

    N/A

    SBB (Lot 8) Shotcrete Retaining Wall

    Waterproofing – retaining Wall – at Mat Pour 1

    N/A

    N/A

     

    Week of July 3, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour - Shear Walls & Columns – Pour 1

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls - Shear Walls & Columns – Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar - Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout and install MEPs - Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds - Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Close Two Side Forms - Shear Walls & Columns – Pour 2

    N/A

    N/A